Item 3.11 Bid Award WH3 WatermainsRequest for
City Council Action
DEPARTMENT INFORMATION
ORIGINATING DEPARTMENT REQUESTOR: MEETING DATE:
Utilities City Engineer Wagner September 14, 2026
PRESENTER(s) REVIEWED BY: ITEM #:
Consent City Administrator/Finance Director Flaherty
Utility Manager Neidermeier
3.11 – Wellhouse 3 Watermain
STRATEGIC VISION
MEETS: THE CITY OF OTSEGO:
Is a strong organization that is committed to leading the community through innovative communication.
X Has proactively expanded infrastructure to responsibly provide core services.
Is committed to delivery of quality emergency service responsive to community needs and expectations in a
cost-effective manner.
Is a social community with diverse housing, service options, and employment opportunities.
Is a distinctive, connected community known for its beauty and natural surroundings.
AGENDA ITEM DETAILS
RECOMMENDATION:
City staff recommend the City Council accept bids and adopt a resolution awarding a contract.
ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED?
Yes No
BACKGROUND/JUSTIFICATION:
Bids were opened for the Dual 18” Watermain Project on September 9, 2026. A total of 19 bids were received as
shown on the attached Bid Tabulation.
This project includes the installation of raw water and treated (domestic) water lines that connect the existing
Wellhouse #3 to the Water Treatment Plant #3 which is in the construction phase. Although being presented for
bid award now, construction is not scheduled to begin until 2027 and will be completed to coincide with the Water
Treatment Plant #3 project.
Kirchoff Construction Inc. of Albertville, Minnesota is the apparent responsible low bidder at $1,400,013.56. The
Engineer’s Estimate presented for approval of the plans and specifications was $1,609,746.70. The Capital
Improvement Plan (CIP) includes $2,058,000 to fund this project. As bid, the total estimate of construction,
engineering, and construction contingency totals $1,680,016, within the CIP budgeted amount. This project is being
funded by a combination of federal grant, state grant, loan financing through MPFA, and local funds.
City staff recommend awarding the contract to the low bidder, Kirchoff Construction Inc. They have completed
projects with other Engineers in our office in the past; the work was completed to specifications and in a timely
manner.
SUPPORTING DOCUMENTS ATTACHED:
•Engineer’s Estimate
•Bid Tabulation
•Resolution 2026-78
POSSIBLE MOTION
PLEASE WORD MOTION AS YOU WOULD LIKE IT TO APPEAR IN THE MINUTES:
Motion to adopt Resolution 2026-78 Accepting Bids and Awarding Contract for the Dual 18” Watermain Project to
Kirchoff Construction Inc. of Albertville, Minnesota in the amount of $1,400,013.56.
BUDGET INFORMATION
FUNDING: BUDGETED:
Fund 601 – Drinking Water Utility
Yes
8/3/2026
ITEM NO.SPEC. REF.DESCRIPTION UNIT
UNIT
COST
TOTAL
ESTIMATED
QUANTITY
TOTAL
ESTIMATED
COST
1 2021.501 MOBILIZATION LUMP SUM 107,614.10$ 1$ 107,614.10$
2 2104.503 SAWING BITUMINOUS PAVEMENT - FULL DEPTH LIN FT 5.06$ 150$ 759.00$
3 2104.504 REMOVE BITUMINOUS PAVEMENT SQ YD 8.15$ 100$ 815.00$
4 2211.509 AGGREGATE BASE CLASS 5 TON 31.90$ 50$ 1,595.00$
5 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GALLON 11.55$ 8$ 92.40$
6 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,C)TON 283.80$ 10$ 2,838.00$
7 2360.509 TYPE SP 12.5 NON WEARING COURST MIXTURE (2,C)TON 254.10$ 19$ 4,827.90$
8 2503.603 30" STEEL CASING PIPE (JACKED)LIN FT 667.70$ 215$ 143,555.50$
9 2504.602 CONNECT TO EXISTING WATERMAIN EACH 2,750.00$ 1$ 2,750.00$
10 2504.602 HYDRANT 8' - 0" BURY DEPTH EACH 7,700.00$ 4$ 30,800.00$
11 2504.602 HYDRANT 12' - 0" BURY DEPTH EACH 8,250.00$ 2$ 16,500.00$
12 2504.602 2" CORPORATION STOP EACH 880.00$ 2$ 1,760.00$
13 2504.602 6" GATE VALVE AND BOX EACH 2,860.00$ 6$ 17,160.00$
14 2504.602 18" BUTTERFLY VALVE AND BOX EACH 7,700.00$ 7$ 53,900.00$
15 2504.603 2" TYPE K COPPER PIPE LIN FT 110.00$ 30$ 3,300.00$
16 2504.603 6" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 102.30$ 56$ 5,728.80$
17 2504.603 12" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 148.50$ 72$ 10,692.00$
18 2504.603 16" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 242.00$ 22$ 5,324.00$
19 2504.603 18" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 240.00$ 3,866$ 927,840.00$
20 2504.603 22" WATERMAIN HDPE DIRECTIONAL DRILL LIN FT 275.00$ 282$ 77,550.00$
21 2504.603 22" WATERMAIN HDPE CARRIER PIPE LIN FT 247.50$ 240$ 59,400.00$
22 2504.604 4" POLYSTYRENE INSULATION SQ YD 82.50$ 100$ 8,250.00$
23 2504.608 DUCTILE IRON TO HDPE FITTINGS EACH 275.00$ 3$ 825.00$
24 2504.608 DUCTILE IRON FITTINGS POUND 12.10$ 7,980$ 96,558.00$
25 2563.601 TRAFFIC CONTROL SUPERVISOR LUMP SUM 2,750.00$ 1$ 2,750.00$
26 2563.601 TRAFFIC CONTROL LUMP SUM 8,250.00$ 1$ 8,250.00$
27 2573.501 STABILIZED CONSTRUCTION EXIT LUMP SUM 1,595.00$ 1$ 1,595.00$
28 2573.501 EROSION CONTROL SUPERVISOR LUMP SUM 2,750.00$ 1$ 2,750.00$
29 2573.502 EROSION CONTROL INLET PROTECTION EACH 220.00$ 2$ 440.00$
30 2573.503 SILT FENCE TYPE; MS LIN FT 2.20$ 4,785$ 10,527.00$
31 2575.501 TURF ESTABLISHMENT LUMP SUM 3,000.00$ 1$ 3,000.00$
TOTAL $1,609,746.70
DUAL 18" WATERMAIN PROJECT NO.26-04
for
ENGINEER'S ESTIMATE
CITY OF OTSEGO
S:\Municipal\Otsego\544 Water Treatement #3 - 2-(18 in)\B-PROJECT DEVELOPMENT\3-DESIGN\OT544 SCHEDULES AND ESTIMATE
1 of 1
BID TABULATION
CITY OF OTSEGO
DUAL 18" WATERMAIN PROJECT
Bids were opened at 2:00 p.m., September 9, 2026.
There were nineteen (19) bids received, as shown herein.
UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION
1 2021.501 MOBILIZATION LUMP SUM 1 $18,802.08 $18,802.08 $52,900.00 $52,900.00 $80,000.00 $80,000.00
2 2104.503 SAWING BITUMINOUS PAVEMENT - FULL DEPTH LIN FT 150 $5.32 $798.00 $3.80 $570.00 $3.00 $450.00
3 2104.504 REMOVE BITUMINOUS PAVEMENT SQ YD 100 $10.65 $1,065.00 $8.40 $840.00 $15.00 $1,500.00
4 2211.509 AGGREGATE BASE CLASS 5 TON 50 $17.41 $870.50 $30.35 $1,517.50 $60.00 $3,000.00
5 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GALLON 8 $10.65 $85.20 $15.00 $120.00 $16.00 $128.00
6 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,C)TON 10 $106.50 $1,065.00 $274.00 $2,740.00 $355.00 $3,550.00
7 2360.509 TYPE SP 12.5 NON WEARING COURST MIXTURE (2,C)TON 19 $106.50 $2,023.50 $367.05 $6,973.95 $290.00 $5,510.00
8 2503.603 30 STEEL CASING PIPE (HORIZONTAL DIRECTIONAL DRILLED or JACK & BORE CONSTRUCTION)LIN FT 215 $907.94 $195,207.10 $981.15 $210,947.25 $880.00 $189,200.00
9 2504.602 CONNECT TO EXISTING WATERMAIN EACH 1 $13,166.10 $13,166.10 $10,034.25 $10,034.25 $9,000.00 $9,000.00
10 2504.602 HYDRANT 8' - 0" BURY DEPTH EACH 4 $7,137.73 $28,550.92 $6,968.90 $27,875.60 $8,000.00 $32,000.00
11 2504.602 HYDRANT 12' - 0" BURY DEPTH EACH 2 $7,974.36 $15,948.72 $7,761.95 $15,523.90 $10,000.00 $20,000.00
12 2504.602 2" CORPORATION STOP EACH 2 $777.93 $1,555.86 $1,243.70 $2,487.40 $2,500.00 $5,000.00
13 2504.602 6" GATE VALVE AND BOX EACH 6 $2,940.15 $17,640.90 $2,595.95 $15,575.70 $3,000.00 $18,000.00
14 2504.602 18" BUTTERFLY VALVE AND BOX EACH 7 $12,380.20 $86,661.40 $12,514.60 $87,602.20 $15,000.00 $105,000.00
15 2504.603 2" TYPE K COPPER PIPE LIN FT 30 $101.00 $3,030.00 $69.45 $2,083.50 $80.00 $2,400.00
16 2504.603 6" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 56 $52.21 $2,923.76 $76.20 $4,267.20 $140.00 $7,840.00
17 2504.603 12" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 72 $106.34 $7,656.48 $155.60 $11,203.20 $100.00 $7,200.00
18 2504.603 16" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 22 $133.91 $2,946.02 $276.30 $6,078.60 $300.00 $6,600.00
19 2504.603 18" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 3866 $151.51 $585,737.66 $160.05 $618,753.30 $180.00 $695,880.00
20 2504.603 22" WATERMAIN HDPE DIRECTIONAL DRILL LIN FT 282 $472.22 $133,166.04 $385.20 $108,626.40 $400.00 $112,800.00
21 2504.603 22" WATERMAIN HDPE CARRIER PIPE LIN FT 240 $143.44 $34,425.60 $238.20 $57,168.00 $160.00 $38,400.00
22 2504.604 4" POLYSTYRENE INSULATION SQ YD 100 $46.92 $4,692.00 $73.00 $7,300.00 $60.00 $6,000.00
23 2504.608 DUCTILE IRON TO HDPE FITTINGS EACH 3 $6,697.76 $20,093.28 $9,290.55 $27,871.65 $7,000.00 $21,000.00
24 2504.608 DUCTILE IRON FITTINGS POUND 7980 $19.96 $159,280.80 $19.50 $155,610.00 $10.00 $79,800.00
25 2563.601 TRAFFIC CONTROL SUPERVISOR LUMP SUM 1 $319.49 $319.49 $1,926.50 $1,926.50 $200.00 $200.00
26 2563.601 TRAFFIC CONTROL LUMP SUM 1 $12,650.82 $12,650.82 $9,795.00 $9,795.00 $25,000.00 $25,000.00
27 2573.501 STABILIZED CONSTRUCTION EXIT LUMP SUM 1 $1,086.99 $1,086.99 $0.01 $0.01 $600.00 $600.00
28 2573.501 EROSION CONTROL SUPERVISOR LUMP SUM 1 $1,216.57 $1,216.57 $1,926.50 $1,926.50 $400.00 $400.00
29 2573.502 EROSION CONTROL INLET PROTECTION EACH 2 $212.99 $425.98 $194.40 $388.80 $200.00 $400.00
30 2573.503 SILT FENCE TYPE; MS LIN FT 4785 $3.73 $17,848.05 $3.00 $14,355.00 $1.00 $4,785.00
31 2575.501 TURF ESTABLISHMENT LUMP SUM 1 $29,073.74 $29,073.74 $10,025.00 $10,025.00 $10,000.00 $10,000.00
$1,400,013.56 $1,473,086.41 $1,491,643.00
Mn/DOT
SPEC. NO.ITEM NO.
Kirchoff Construction Inc.Douglas-Kerr Underground,
L.L.C A-1 Excavating LLC
ESTIMATED
QUANTITYUNITITEM DESCRIPTION
Page 1 of 7
BID TABULATION
CITY OF OTSEGO
DUAL 18" WATERMAIN PROJECT
Bids were opened at 2:00 p.m., September 9, 2026.
There were nineteen (19) bids received, as shown herein.
1 2021.501 MOBILIZATION LUMP SUM 1
2 2104.503 SAWING BITUMINOUS PAVEMENT - FULL DEPTH LIN FT 150
3 2104.504 REMOVE BITUMINOUS PAVEMENT SQ YD 100
4 2211.509 AGGREGATE BASE CLASS 5 TON 50
5 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GALLON 8
6 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,C)TON 10
7 2360.509 TYPE SP 12.5 NON WEARING COURST MIXTURE (2,C)TON 19
8 2503.603 30 STEEL CASING PIPE (HORIZONTAL DIRECTIONAL DRILLED or JACK & BORE CONSTRUCTION)LIN FT 215
9 2504.602 CONNECT TO EXISTING WATERMAIN EACH 1
10 2504.602 HYDRANT 8' - 0" BURY DEPTH EACH 4
11 2504.602 HYDRANT 12' - 0" BURY DEPTH EACH 2
12 2504.602 2" CORPORATION STOP EACH 2
13 2504.602 6" GATE VALVE AND BOX EACH 6
14 2504.602 18" BUTTERFLY VALVE AND BOX EACH 7
15 2504.603 2" TYPE K COPPER PIPE LIN FT 30
16 2504.603 6" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 56
17 2504.603 12" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 72
18 2504.603 16" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 22
19 2504.603 18" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 3866
20 2504.603 22" WATERMAIN HDPE DIRECTIONAL DRILL LIN FT 282
21 2504.603 22" WATERMAIN HDPE CARRIER PIPE LIN FT 240
22 2504.604 4" POLYSTYRENE INSULATION SQ YD 100
23 2504.608 DUCTILE IRON TO HDPE FITTINGS EACH 3
24 2504.608 DUCTILE IRON FITTINGS POUND 7980
25 2563.601 TRAFFIC CONTROL SUPERVISOR LUMP SUM 1
26 2563.601 TRAFFIC CONTROL LUMP SUM 1
27 2573.501 STABILIZED CONSTRUCTION EXIT LUMP SUM 1
28 2573.501 EROSION CONTROL SUPERVISOR LUMP SUM 1
29 2573.502 EROSION CONTROL INLET PROTECTION EACH 2
30 2573.503 SILT FENCE TYPE; MS LIN FT 4785
31 2575.501 TURF ESTABLISHMENT LUMP SUM 1
Mn/DOT
SPEC. NO.ITEM NO.
ESTIMATED
QUANTITYUNITITEM DESCRIPTION UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION
$56,669.40 $56,669.40 $102,800.00 $102,800.00 $80,000.00 $80,000.00
$7.15 $1,072.50 $2.25 $337.50 $5.00 $750.00
$5.66 $566.00 $9.85 $985.00 $7.00 $700.00
$29.99 $1,499.50 $39.45 $1,972.50 $45.00 $2,250.00
$11.00 $88.00 $17.00 $136.00 $15.00 $120.00
$275.00 $2,750.00 $311.00 $3,110.00 $285.00 $2,850.00
$275.00 $5,225.00 $311.00 $5,909.00 $285.00 $5,415.00
$1,010.81 $217,324.15 $1,006.00 $216,290.00 $820.00 $176,300.00
$10,186.49 $10,186.49 $15,000.00 $15,000.00 $2,700.00 $2,700.00
$7,153.32 $28,613.28 $7,787.45 $31,149.80 $8,700.00 $34,800.00
$8,869.40 $17,738.80 $8,358.55 $16,717.10 $9,900.00 $19,800.00
$1,193.71 $2,387.42 $800.00 $1,600.00 $2,000.00 $4,000.00
$2,587.74 $15,526.44 $2,800.00 $16,800.00 $3,000.00 $18,000.00
$12,459.21 $87,214.47 $12,600.00 $88,200.00 $16,000.00 $112,000.00
$90.85 $2,725.50 $66.00 $1,980.00 $89.00 $2,670.00
$75.81 $4,245.36 $151.55 $8,486.80 $84.00 $4,704.00
$130.42 $9,390.24 $119.45 $8,600.40 $136.00 $9,792.00
$238.02 $5,236.44 $177.40 $3,902.80 $190.00 $4,180.00
$162.26 $627,297.16 $160.20 $619,333.20 $218.00 $842,788.00
$429.86 $121,220.52 $403.45 $113,772.90 $460.00 $129,720.00
$295.05 $70,812.00 $198.70 $47,688.00 $147.00 $35,280.00
$53.26 $5,326.00 $65.00 $6,500.00 $54.00 $5,400.00
$6,183.31 $18,549.93 $6,890.50 $20,671.50 $7,800.00 $23,400.00
$18.93 $151,061.40 $21.10 $168,378.00 $0.01 $79.80
$818.06 $818.06 $100.00 $100.00 $500.00 $500.00
$10,775.60 $10,775.60 $18,000.00 $18,000.00 $15,000.00 $15,000.00
$2,920.76 $2,920.76 $3,500.00 $3,500.00 $1,600.00 $1,600.00
$981.68 $981.68 $400.00 $400.00 $1,100.00 $1,100.00
$333.59 $667.18 $217.00 $434.00 $280.00 $560.00
$3.05 $14,594.25 $3.35 $16,029.75 $2.50 $11,962.50
$19,030.00 $19,030.00 $5,000.00 $5,000.00 $15,000.00 $15,000.00
$1,512,513.53 $1,543,784.25 $1,563,421.30
Kuechle Underground Inc.PWS Landwehr Construction, Inc.
Page 2 of 7
BID TABULATION
CITY OF OTSEGO
DUAL 18" WATERMAIN PROJECT
Bids were opened at 2:00 p.m., September 9, 2026.
There were nineteen (19) bids received, as shown herein.
1 2021.501 MOBILIZATION LUMP SUM 1
2 2104.503 SAWING BITUMINOUS PAVEMENT - FULL DEPTH LIN FT 150
3 2104.504 REMOVE BITUMINOUS PAVEMENT SQ YD 100
4 2211.509 AGGREGATE BASE CLASS 5 TON 50
5 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GALLON 8
6 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,C)TON 10
7 2360.509 TYPE SP 12.5 NON WEARING COURST MIXTURE (2,C)TON 19
8 2503.603 30 STEEL CASING PIPE (HORIZONTAL DIRECTIONAL DRILLED or JACK & BORE CONSTRUCTION)LIN FT 215
9 2504.602 CONNECT TO EXISTING WATERMAIN EACH 1
10 2504.602 HYDRANT 8' - 0" BURY DEPTH EACH 4
11 2504.602 HYDRANT 12' - 0" BURY DEPTH EACH 2
12 2504.602 2" CORPORATION STOP EACH 2
13 2504.602 6" GATE VALVE AND BOX EACH 6
14 2504.602 18" BUTTERFLY VALVE AND BOX EACH 7
15 2504.603 2" TYPE K COPPER PIPE LIN FT 30
16 2504.603 6" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 56
17 2504.603 12" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 72
18 2504.603 16" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 22
19 2504.603 18" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 3866
20 2504.603 22" WATERMAIN HDPE DIRECTIONAL DRILL LIN FT 282
21 2504.603 22" WATERMAIN HDPE CARRIER PIPE LIN FT 240
22 2504.604 4" POLYSTYRENE INSULATION SQ YD 100
23 2504.608 DUCTILE IRON TO HDPE FITTINGS EACH 3
24 2504.608 DUCTILE IRON FITTINGS POUND 7980
25 2563.601 TRAFFIC CONTROL SUPERVISOR LUMP SUM 1
26 2563.601 TRAFFIC CONTROL LUMP SUM 1
27 2573.501 STABILIZED CONSTRUCTION EXIT LUMP SUM 1
28 2573.501 EROSION CONTROL SUPERVISOR LUMP SUM 1
29 2573.502 EROSION CONTROL INLET PROTECTION EACH 2
30 2573.503 SILT FENCE TYPE; MS LIN FT 4785
31 2575.501 TURF ESTABLISHMENT LUMP SUM 1
Mn/DOT
SPEC. NO.ITEM NO.
ESTIMATED
QUANTITYUNITITEM DESCRIPTION UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION
$54,141.50 $54,141.50 $80,237.60 $80,237.60 $100,000.00 $100,000.00
$4.00 $600.00 $5.55 $832.50 $3.00 $450.00
$70.00 $7,000.00 $10.00 $1,000.00 $8.00 $800.00
$50.00 $2,500.00 $41.75 $2,087.50 $30.00 $1,500.00
$5.50 $44.00 $0.01 $0.08 $6.00 $48.00
$288.00 $2,880.00 $391.25 $3,912.50 $550.00 $5,500.00
$286.00 $5,434.00 $251.25 $4,773.75 $500.00 $9,500.00
$912.00 $196,080.00 $900.00 $193,500.00 $1,100.00 $236,500.00
$7,300.00 $7,300.00 $17,500.00 $17,500.00 $5,000.00 $5,000.00
$8,500.00 $34,000.00 $8,285.00 $33,140.00 $7,500.00 $30,000.00
$9,300.00 $18,600.00 $9,325.00 $18,650.00 $10,000.00 $20,000.00
$2,400.00 $4,800.00 $1,335.50 $2,671.00 $750.00 $1,500.00
$3,500.00 $21,000.00 $3,425.00 $20,550.00 $2,700.00 $16,200.00
$16,300.00 $114,100.00 $15,875.00 $111,125.00 $14,000.00 $98,000.00
$80.00 $2,400.00 $110.75 $3,322.50 $75.00 $2,250.00
$106.00 $5,936.00 $98.80 $5,532.80 $87.00 $4,872.00
$123.00 $8,856.00 $127.90 $9,208.80 $136.00 $9,792.00
$290.00 $6,380.00 $875.00 $19,250.00 $186.00 $4,092.00
$185.00 $715,210.00 $161.75 $625,325.50 $171.00 $661,086.00
$325.00 $91,650.00 $503.40 $141,958.80 $390.00 $109,980.00
$230.00 $55,200.00 $140.15 $33,636.00 $240.00 $57,600.00
$90.00 $9,000.00 $47.35 $4,735.00 $50.00 $5,000.00
$7,200.00 $21,600.00 $6,500.00 $19,500.00 $8,000.00 $24,000.00
$19.00 $151,620.00 $16.50 $131,670.00 $14.00 $111,720.00
$4,000.00 $4,000.00 $2,400.00 $2,400.00 $3,000.00 $3,000.00
$3,500.00 $3,500.00 $16,865.92 $16,865.92 $20,000.00 $20,000.00
$4,500.00 $4,500.00 $2,500.00 $2,500.00 $1,500.00 $1,500.00
$4,000.00 $4,000.00 $865.00 $865.00 $3,000.00 $3,000.00
$210.00 $420.00 $360.00 $720.00 $150.00 $300.00
$2.10 $10,048.50 $3.35 $16,029.75 $2.50 $11,962.50
$6,200.00 $6,200.00 $49,750.00 $49,750.00 $25,000.00 $25,000.00
$1,569,000.00 $1,573,250.00 $1,580,152.50
S.M. Hentges & Sons, Inc.Rachel Contracting, LLC C&L Excavating, Inc
Page 3 of 7
BID TABULATION
CITY OF OTSEGO
DUAL 18" WATERMAIN PROJECT
Bids were opened at 2:00 p.m., September 9, 2026.
There were nineteen (19) bids received, as shown herein.
1 2021.501 MOBILIZATION LUMP SUM 1
2 2104.503 SAWING BITUMINOUS PAVEMENT - FULL DEPTH LIN FT 150
3 2104.504 REMOVE BITUMINOUS PAVEMENT SQ YD 100
4 2211.509 AGGREGATE BASE CLASS 5 TON 50
5 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GALLON 8
6 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,C)TON 10
7 2360.509 TYPE SP 12.5 NON WEARING COURST MIXTURE (2,C)TON 19
8 2503.603 30 STEEL CASING PIPE (HORIZONTAL DIRECTIONAL DRILLED or JACK & BORE CONSTRUCTION)LIN FT 215
9 2504.602 CONNECT TO EXISTING WATERMAIN EACH 1
10 2504.602 HYDRANT 8' - 0" BURY DEPTH EACH 4
11 2504.602 HYDRANT 12' - 0" BURY DEPTH EACH 2
12 2504.602 2" CORPORATION STOP EACH 2
13 2504.602 6" GATE VALVE AND BOX EACH 6
14 2504.602 18" BUTTERFLY VALVE AND BOX EACH 7
15 2504.603 2" TYPE K COPPER PIPE LIN FT 30
16 2504.603 6" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 56
17 2504.603 12" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 72
18 2504.603 16" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 22
19 2504.603 18" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 3866
20 2504.603 22" WATERMAIN HDPE DIRECTIONAL DRILL LIN FT 282
21 2504.603 22" WATERMAIN HDPE CARRIER PIPE LIN FT 240
22 2504.604 4" POLYSTYRENE INSULATION SQ YD 100
23 2504.608 DUCTILE IRON TO HDPE FITTINGS EACH 3
24 2504.608 DUCTILE IRON FITTINGS POUND 7980
25 2563.601 TRAFFIC CONTROL SUPERVISOR LUMP SUM 1
26 2563.601 TRAFFIC CONTROL LUMP SUM 1
27 2573.501 STABILIZED CONSTRUCTION EXIT LUMP SUM 1
28 2573.501 EROSION CONTROL SUPERVISOR LUMP SUM 1
29 2573.502 EROSION CONTROL INLET PROTECTION EACH 2
30 2573.503 SILT FENCE TYPE; MS LIN FT 4785
31 2575.501 TURF ESTABLISHMENT LUMP SUM 1
Mn/DOT
SPEC. NO.ITEM NO.
ESTIMATED
QUANTITYUNITITEM DESCRIPTION UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION
$70,000.00 $70,000.00 $33,000.00 $33,000.00 $53,830.27 $53,830.27
$5.50 $825.00 $6.00 $900.00 $2.00 $300.00
$10.00 $1,000.00 $6.00 $600.00 $4.47 $447.00
$24.00 $1,200.00 $40.00 $2,000.00 $52.08 $2,604.00
$35.00 $280.00 $20.00 $160.00 $11.74 $93.92
$250.00 $2,500.00 $300.00 $3,000.00 $229.00 $2,290.00
$250.00 $4,750.00 $300.00 $5,700.00 $229.00 $4,351.00
$1,300.00 $279,500.00 $1,000.00 $215,000.00 $1,197.25 $257,408.75
$6,000.00 $6,000.00 $17,500.00 $17,500.00 $8,892.55 $8,892.55
$7,350.00 $29,400.00 $7,625.00 $30,500.00 $6,806.45 $27,225.80
$9,400.00 $18,800.00 $9,250.00 $18,500.00 $9,183.63 $18,367.26
$2,790.00 $5,580.00 $3,000.00 $6,000.00 $2,697.83 $5,395.66
$3,025.00 $18,150.00 $3,225.00 $19,350.00 $3,475.78 $20,854.68
$14,575.00 $102,025.00 $15,000.00 $105,000.00 $13,914.81 $97,403.67
$80.00 $2,400.00 $70.00 $2,100.00 $147.30 $4,419.00
$120.00 $6,720.00 $60.00 $3,360.00 $85.16 $4,768.96
$150.00 $10,800.00 $120.00 $8,640.00 $130.33 $9,383.76
$330.00 $7,260.00 $220.00 $4,840.00 $175.03 $3,850.66
$180.00 $695,880.00 $175.00 $676,550.00 $178.09 $688,495.94
$450.00 $126,900.00 $540.00 $152,280.00 $321.57 $90,682.74
$160.00 $38,400.00 $320.00 $76,800.00 $176.91 $42,458.40
$32.00 $3,200.00 $45.00 $4,500.00 $22.96 $2,296.00
$6,675.00 $20,025.00 $9,500.00 $28,500.00 $6,836.16 $20,508.48
$17.50 $139,650.00 $20.00 $159,600.00 $24.69 $197,026.20
$1.00 $1.00 $1,000.00 $1,000.00 $1,500.00 $1,500.00
$15,700.00 $15,700.00 $18,000.00 $18,000.00 $11,787.07 $11,787.07
$1.00 $1.00 $5,000.00 $5,000.00 $2,682.23 $2,682.23
$1.00 $1.00 $3,000.00 $3,000.00 $1,500.00 $1,500.00
$300.00 $600.00 $250.00 $500.00 $500.00 $1,000.00
$3.50 $16,747.50 $2.30 $11,005.50 $2.25 $10,766.25
$8,500.00 $8,500.00 $22,000.00 $22,000.00 $67,000.00 $67,000.00
$1,632,795.50 $1,634,885.50 $1,659,590.25
Burschville Construction Inc G M Contracting, Inc.New Look Contracting, Inc.
Page 4 of 7
BID TABULATION
CITY OF OTSEGO
DUAL 18" WATERMAIN PROJECT
Bids were opened at 2:00 p.m., September 9, 2026.
There were nineteen (19) bids received, as shown herein.
1 2021.501 MOBILIZATION LUMP SUM 1
2 2104.503 SAWING BITUMINOUS PAVEMENT - FULL DEPTH LIN FT 150
3 2104.504 REMOVE BITUMINOUS PAVEMENT SQ YD 100
4 2211.509 AGGREGATE BASE CLASS 5 TON 50
5 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GALLON 8
6 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,C)TON 10
7 2360.509 TYPE SP 12.5 NON WEARING COURST MIXTURE (2,C)TON 19
8 2503.603 30 STEEL CASING PIPE (HORIZONTAL DIRECTIONAL DRILLED or JACK & BORE CONSTRUCTION)LIN FT 215
9 2504.602 CONNECT TO EXISTING WATERMAIN EACH 1
10 2504.602 HYDRANT 8' - 0" BURY DEPTH EACH 4
11 2504.602 HYDRANT 12' - 0" BURY DEPTH EACH 2
12 2504.602 2" CORPORATION STOP EACH 2
13 2504.602 6" GATE VALVE AND BOX EACH 6
14 2504.602 18" BUTTERFLY VALVE AND BOX EACH 7
15 2504.603 2" TYPE K COPPER PIPE LIN FT 30
16 2504.603 6" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 56
17 2504.603 12" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 72
18 2504.603 16" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 22
19 2504.603 18" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 3866
20 2504.603 22" WATERMAIN HDPE DIRECTIONAL DRILL LIN FT 282
21 2504.603 22" WATERMAIN HDPE CARRIER PIPE LIN FT 240
22 2504.604 4" POLYSTYRENE INSULATION SQ YD 100
23 2504.608 DUCTILE IRON TO HDPE FITTINGS EACH 3
24 2504.608 DUCTILE IRON FITTINGS POUND 7980
25 2563.601 TRAFFIC CONTROL SUPERVISOR LUMP SUM 1
26 2563.601 TRAFFIC CONTROL LUMP SUM 1
27 2573.501 STABILIZED CONSTRUCTION EXIT LUMP SUM 1
28 2573.501 EROSION CONTROL SUPERVISOR LUMP SUM 1
29 2573.502 EROSION CONTROL INLET PROTECTION EACH 2
30 2573.503 SILT FENCE TYPE; MS LIN FT 4785
31 2575.501 TURF ESTABLISHMENT LUMP SUM 1
Mn/DOT
SPEC. NO.ITEM NO.
ESTIMATED
QUANTITYUNITITEM DESCRIPTION UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION
$83,000.00 $83,000.00 $45,300.00 $45,300.00 $100,000.00 $100,000.00
$5.00 $750.00 $2.20 $330.00 $10.00 $1,500.00
$12.50 $1,250.00 $10.50 $1,050.00 $20.00 $2,000.00
$36.00 $1,800.00 $47.50 $2,375.00 $50.00 $2,500.00
$15.00 $120.00 $16.50 $132.00 $10.00 $80.00
$274.00 $2,740.00 $305.00 $3,050.00 $200.00 $2,000.00
$417.00 $7,923.00 $305.00 $5,795.00 $200.00 $3,800.00
$1,025.00 $220,375.00 $1,050.00 $225,750.00 $1,000.00 $215,000.00
$8,000.00 $8,000.00 $15,500.00 $15,500.00 $25,000.00 $25,000.00
$7,338.00 $29,352.00 $10,750.00 $43,000.00 $7,500.00 $30,000.00
$8,800.00 $17,600.00 $12,650.00 $25,300.00 $8,500.00 $17,000.00
$586.00 $1,172.00 $4,150.00 $8,300.00 $2,000.00 $4,000.00
$2,637.00 $15,822.00 $4,060.00 $24,360.00 $3,500.00 $21,000.00
$12,577.00 $88,039.00 $19,950.00 $139,650.00 $14,000.00 $98,000.00
$140.00 $4,200.00 $161.00 $4,830.00 $100.00 $3,000.00
$75.00 $4,200.00 $109.00 $6,104.00 $130.00 $7,280.00
$145.00 $10,440.00 $188.00 $13,536.00 $180.00 $12,960.00
$185.00 $4,070.00 $231.00 $5,082.00 $195.00 $4,290.00
$198.00 $765,468.00 $168.00 $649,488.00 $200.00 $773,200.00
$408.00 $115,056.00 $473.00 $133,386.00 $520.00 $146,640.00
$169.00 $40,560.00 $265.00 $63,600.00 $250.00 $60,000.00
$71.00 $7,100.00 $70.00 $7,000.00 $60.00 $6,000.00
$7,930.00 $23,790.00 $12,350.00 $37,050.00 $16,000.00 $48,000.00
$19.00 $151,620.00 $25.50 $203,490.00 $18.00 $143,640.00
$1,500.00 $1,500.00 $9,010.00 $9,010.00 $1.00 $1.00
$15,000.00 $15,000.00 $17,800.00 $17,800.00 $25,000.00 $25,000.00
$2,500.00 $2,500.00 $2,120.00 $2,120.00 $2,500.00 $2,500.00
$1,500.00 $1,500.00 $1,320.00 $1,320.00 $1.00 $1.00
$450.00 $900.00 $225.00 $450.00 $200.00 $400.00
$2.75 $13,158.75 $2.80 $13,398.00 $2.00 $9,570.00
$25,000.00 $25,000.00 $49,425.00 $49,425.00 $20,000.00 $20,000.00
$1,664,005.75 $1,756,981.00 $1,784,362.00
S R Weidema, Incorporated Minger Construction Co. Inc.Ryan Contracting Co.
Page 5 of 7
BID TABULATION
CITY OF OTSEGO
DUAL 18" WATERMAIN PROJECT
Bids were opened at 2:00 p.m., September 9, 2026.
There were nineteen (19) bids received, as shown herein.
1 2021.501 MOBILIZATION LUMP SUM 1
2 2104.503 SAWING BITUMINOUS PAVEMENT - FULL DEPTH LIN FT 150
3 2104.504 REMOVE BITUMINOUS PAVEMENT SQ YD 100
4 2211.509 AGGREGATE BASE CLASS 5 TON 50
5 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GALLON 8
6 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,C)TON 10
7 2360.509 TYPE SP 12.5 NON WEARING COURST MIXTURE (2,C)TON 19
8 2503.603 30 STEEL CASING PIPE (HORIZONTAL DIRECTIONAL DRILLED or JACK & BORE CONSTRUCTION)LIN FT 215
9 2504.602 CONNECT TO EXISTING WATERMAIN EACH 1
10 2504.602 HYDRANT 8' - 0" BURY DEPTH EACH 4
11 2504.602 HYDRANT 12' - 0" BURY DEPTH EACH 2
12 2504.602 2" CORPORATION STOP EACH 2
13 2504.602 6" GATE VALVE AND BOX EACH 6
14 2504.602 18" BUTTERFLY VALVE AND BOX EACH 7
15 2504.603 2" TYPE K COPPER PIPE LIN FT 30
16 2504.603 6" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 56
17 2504.603 12" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 72
18 2504.603 16" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 22
19 2504.603 18" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 3866
20 2504.603 22" WATERMAIN HDPE DIRECTIONAL DRILL LIN FT 282
21 2504.603 22" WATERMAIN HDPE CARRIER PIPE LIN FT 240
22 2504.604 4" POLYSTYRENE INSULATION SQ YD 100
23 2504.608 DUCTILE IRON TO HDPE FITTINGS EACH 3
24 2504.608 DUCTILE IRON FITTINGS POUND 7980
25 2563.601 TRAFFIC CONTROL SUPERVISOR LUMP SUM 1
26 2563.601 TRAFFIC CONTROL LUMP SUM 1
27 2573.501 STABILIZED CONSTRUCTION EXIT LUMP SUM 1
28 2573.501 EROSION CONTROL SUPERVISOR LUMP SUM 1
29 2573.502 EROSION CONTROL INLET PROTECTION EACH 2
30 2573.503 SILT FENCE TYPE; MS LIN FT 4785
31 2575.501 TURF ESTABLISHMENT LUMP SUM 1
Mn/DOT
SPEC. NO.ITEM NO.
ESTIMATED
QUANTITYUNITITEM DESCRIPTION UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION
$127,602.04 $127,602.04 $150,000.00 $150,000.00 $70,000.00 $70,000.00
$5.00 $750.00 $4.60 $690.00 $5.00 $750.00
$9.49 $949.00 $32.80 $3,280.00 $15.00 $1,500.00
$40.00 $2,000.00 $49.60 $2,480.00 $85.00 $4,250.00
$10.00 $80.00 $10.60 $84.80 $15.00 $120.00
$195.00 $1,950.00 $206.00 $2,060.00 $250.00 $2,500.00
$314.80 $5,981.20 $206.00 $3,914.00 $250.00 $4,750.00
$1,291.48 $277,668.20 $1,320.00 $283,800.00 $1,410.00 $303,150.00
$7,413.83 $7,413.83 $10,000.00 $10,000.00 $15,000.00 $15,000.00
$8,005.58 $32,022.32 $8,040.00 $32,160.00 $7,500.00 $30,000.00
$8,557.71 $17,115.42 $9,480.00 $18,960.00 $9,500.00 $19,000.00
$1,582.34 $3,164.68 $3,140.00 $6,280.00 $4,500.00 $9,000.00
$3,102.36 $18,614.16 $3,200.00 $19,200.00 $3,400.00 $20,400.00
$13,707.03 $95,949.21 $15,500.00 $108,500.00 $16,000.00 $112,000.00
$128.30 $3,849.00 $93.70 $2,811.00 $100.00 $3,000.00
$167.63 $9,387.28 $111.50 $6,244.00 $120.00 $6,720.00
$155.40 $11,188.80 $163.50 $11,772.00 $165.00 $11,880.00
$433.35 $9,533.70 $284.00 $6,248.00 $250.00 $5,500.00
$181.55 $701,872.30 $172.00 $664,952.00 $190.00 $734,540.00
$395.15 $111,432.30 $640.50 $180,621.00 $485.00 $136,770.00
$322.52 $77,404.80 $260.50 $62,520.00 $255.00 $61,200.00
$68.71 $6,871.00 $12.70 $1,270.00 $65.00 $6,500.00
$11,025.96 $33,077.88 $11,100.00 $33,300.00 $9,000.00 $27,000.00
$23.23 $185,375.40 $22.10 $176,358.00 $22.00 $175,560.00
$3,000.00 $3,000.00 $0.01 $0.01 $2,500.00 $2,500.00
$13,590.00 $13,590.00 $3,170.00 $3,170.00 $25,000.00 $25,000.00
$2,500.00 $2,500.00 $4,220.00 $4,220.00 $2,500.00 $2,500.00
$5,000.00 $5,000.00 $1,500.00 $1,500.00 $5,000.00 $5,000.00
$500.00 $1,000.00 $211.50 $423.00 $250.00 $500.00
$3.92 $18,757.20 $2.60 $12,441.00 $4.00 $19,140.00
$37,960.68 $37,960.68 $24,700.00 $24,700.00 $24,000.00 $24,000.00
$1,823,060.40 $1,833,958.81 $1,839,730.00
Meyer Contracting Inc.RL Larson Excavating Inc.J.R. Ferche, Inc.
Page 6 of 7
BID TABULATION
CITY OF OTSEGO
DUAL 18" WATERMAIN PROJECT
Bids were opened at 2:00 p.m., September 9, 2026.
There were nineteen (19) bids received, as shown herein.
1 2021.501 MOBILIZATION LUMP SUM 1
2 2104.503 SAWING BITUMINOUS PAVEMENT - FULL DEPTH LIN FT 150
3 2104.504 REMOVE BITUMINOUS PAVEMENT SQ YD 100
4 2211.509 AGGREGATE BASE CLASS 5 TON 50
5 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GALLON 8
6 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,C)TON 10
7 2360.509 TYPE SP 12.5 NON WEARING COURST MIXTURE (2,C)TON 19
8 2503.603 30 STEEL CASING PIPE (HORIZONTAL DIRECTIONAL DRILLED or JACK & BORE CONSTRUCTION)LIN FT 215
9 2504.602 CONNECT TO EXISTING WATERMAIN EACH 1
10 2504.602 HYDRANT 8' - 0" BURY DEPTH EACH 4
11 2504.602 HYDRANT 12' - 0" BURY DEPTH EACH 2
12 2504.602 2" CORPORATION STOP EACH 2
13 2504.602 6" GATE VALVE AND BOX EACH 6
14 2504.602 18" BUTTERFLY VALVE AND BOX EACH 7
15 2504.603 2" TYPE K COPPER PIPE LIN FT 30
16 2504.603 6" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 56
17 2504.603 12" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 72
18 2504.603 16" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 22
19 2504.603 18" WATERMAIN DUCTILE IRON CL 52 OPEN CUT LIN FT 3866
20 2504.603 22" WATERMAIN HDPE DIRECTIONAL DRILL LIN FT 282
21 2504.603 22" WATERMAIN HDPE CARRIER PIPE LIN FT 240
22 2504.604 4" POLYSTYRENE INSULATION SQ YD 100
23 2504.608 DUCTILE IRON TO HDPE FITTINGS EACH 3
24 2504.608 DUCTILE IRON FITTINGS POUND 7980
25 2563.601 TRAFFIC CONTROL SUPERVISOR LUMP SUM 1
26 2563.601 TRAFFIC CONTROL LUMP SUM 1
27 2573.501 STABILIZED CONSTRUCTION EXIT LUMP SUM 1
28 2573.501 EROSION CONTROL SUPERVISOR LUMP SUM 1
29 2573.502 EROSION CONTROL INLET PROTECTION EACH 2
30 2573.503 SILT FENCE TYPE; MS LIN FT 4785
31 2575.501 TURF ESTABLISHMENT LUMP SUM 1
Mn/DOT
SPEC. NO.ITEM NO.
ESTIMATED
QUANTITYUNITITEM DESCRIPTION UNIT PRICE EXTENSION
$95,000.00 $95,000.00
$5.00 $750.00
$27.50 $2,750.00
$80.00 $4,000.00
$0.01 $0.08
$380.00 $3,800.00
$260.00 $4,940.00
$1,015.00 $218,225.00
$9,500.00 $9,500.00
$9,550.00 $38,200.00
$9,650.00 $19,300.00
$975.00 $1,950.00
$3,975.00 $23,850.00
$17,000.00 $119,000.00
$105.00 $3,150.00
$115.00 $6,440.00
$154.00 $11,088.00
$220.00 $4,840.00
$211.00 $815,726.00
$470.00 $132,540.00
$245.00 $58,800.00
$67.00 $6,700.00
$7,250.00 $21,750.00
$24.00 $191,520.00
$750.00 $750.00
$56,500.00 $56,500.00
$1,000.00 $1,000.00
$750.00 $750.00
$500.00 $1,000.00
$2.50 $11,962.50
$12,000.00 $12,000.00
$1,877,781.58
Bituminous Roadways Inc.
Page 7 of 7
1
CITY OF OTSEGO
COUNTY OF WRIGHT
STATE OF MINNESOTA
RESOLUTION NO: 2026-78
ACCEPTING BIDS AND AWARDING CONTRACT
WHEREAS, the City has approved plans and specifications for the Dual 18” Watermain Project and advertised for bids; and
WHEREAS, pursuant to the advertisement for bids for the construction of the Dual 18” Watermain Project, bids were
received, opened on September 9, 2026, and tabulated according to law, and the following bids were received complying
with the advertisement; and
WHEREAS, it appears that Kirchoff Construction Inc., of Albertville, Minnesota is the lowest responsible bidder for the Base
Bid; and
WHEREAS, the City will accept the Base Bid in the amount of $1,400,013.56 from Kirchoff Construction Inc.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF OTSEGO, MINNESOTA:
1. The Mayor and City Clerk are hereby authorized and directed to enter into a contract with Kirchoff Construction Inc.,
of Albertville, Minnesota in the name of the City of Otsego for the Dual 18” Watermain Project, according to the
plans and specifications therefore approved by the City Council and on file in the office of the City Clerk.
Base Bid
Kirchoff Construction Inc. $1,400,013.56
Douglas-Kerr Underground, LLC $1,473,086.41
A-1 Excavating LLC $1,491,643.00
PWS $1,512,513.53
Landwehr Construction, Inc. $1,543,784.25
Kuechle Underground Inc. $1,563,421.30
S.M. Hentges & Sons, Inc. $1,569,000.00
Rachel Contracting, LLC $1,573,250.00
C&L Excavating, Inc $1,580,152.50
New Look Contracting, Inc. $1,632,795.50
Burschville Construction Inc $1,634,885.50
G M Contracting, Inc. $1,659,590.25
S R Weidema, Incorporated $1,664,005.75
Minger Construction Co. Inc. $1,756,981.00
Ryan Contracting Co. $1,784,362.00
Meyer Contracting Inc. $1,823,060.40
RL Larson Excavating Inc. $1,833,958.81
J.R. Ferche, Inc. $1,839,730.00
Bituminous Roadways Inc. $1,877,781.58
2
2. The City Clerk is hereby authorized and directed to return forthwith to all bidders the bid bond made with their bids,
except that the bid bond of the successful bidder and the next lowest bidder shall be retained until a contract has
been signed.
ADOPTED by the Otsego City Council this 14th day of September, 2026.
MOTION BY:
SECONDED BY:
IN FAVOR:
OPPOSED:
CITY OF OTSEGO
__________________________________
Jessica L. Stockamp, Mayor
ATTEST:
__________________________________
Audra Etzel, City Clerk