Item 3.12 2026 Greenway Trail Projects Accepting Bids and Awarding Contract
Request for
City Council Action
DEPARTMENT INFORMATION
ORIGINATING DEPARTMENT REQUESTOR: MEETING DATE:
Parks and Recreation City Engineer Wagner August 24, 2026
PRESENTER(s) REVIEWED BY: ITEM #:
Consent City Administrator/Finance Director Flaherty 3.12 – Greenway Trail Projects
STRATEGIC VISION
MEETS: THE CITY OF OTSEGO:
Is a strong organization that is committed to leading the community through innovative communication.
X Has proactively expanded infrastructure to responsibly provide core services.
Is committed to delivery of quality emergency service responsive to community needs and expectations in a
cost-effective manner.
Is a social community with diverse housing, service options, and employment opportunities.
Is a distinctive, connected community known for its beauty and natural surroundings.
AGENDA ITEM DETAILS
RECOMMENDATION:
City staff recommend the City Council accept bids and adopt a resolution awarding a contract.
ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED?
Yes No
BACKGROUND/JUSTIFICATION:
Bids were opened for the 2026 Meadows of Otsego Trail Project No. 26-03 on August 19, 2026. A total of 10 bids
were received as shown on the attached Bid Tabulation.
Matt Bullock Contracting Co, Inc., of St. Michael, Minnesota is the apparent responsible low bidder at $175,670.67. At
their July 27, 2026, meeting, the City Council authorized procurement of the wetland bridges for the project in the
amount of $246,796. As bid, the total estimate of construction, wetland bridges, engineering, and construction
contingency totals $485,837. The Capital Improvement Plan included funding in the amount of $675,450.
City staff recommend awarding the contract to the low bidder, Matt Bullock Contracting Co., Inc. They have completed
projects within the City of Otsego in the past; and are currently working on the Lily Pond Park.
SUPPORTING DOCUMENTS ATTACHED:
• Bid Tabulation
• Resolution 2026-73
POSSIBLE MOTION
PLEASE WORD MOTION AS YOU WOULD LIKE IT TO APPEAR IN THE MINUTES:
Motion to adopt Resolution 2026-73 Accepting Bids and Awarding Contract for the 2026 Meadows of Otsego Trail
Project, City Project No. 26-03 to Matt Bullock Contracting Co, Inc., of St. Michael, Minnesota in the amount of
$175,670.67.
BUDGET INFORMATION
FUNDING: BUDGETED:
Fund 203 – Park Development
Yes
BID TABULATION
CITY OF OTSEGO
2026 MEADOWS OF OTSEGO TRAIL PROJECT
Bids were opened at 2:00 p.m., August 19, 2026.
There were ten (10) bids received, as shown herein.
UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION
1 2021.501 MOBILIZATION LS 1 $11,275.00 $11,275.00 $19,850.00 $19,850.00 $15,000.00 $15,000.00
2 2101.505 CLEARING AC 1.55 $3,937.45 $6,103.05 $8,514.00 $13,196.70 $7,000.00 $10,850.00
3 2101.505 GRUBBING AC 1.55 $3,937.45 $6,103.05 $6,050.00 $9,377.50 $5,000.00 $7,750.00
4 2104.503 SAWING BITUMINOUS PAVEMENT - FULL DEPTH LF 40 $8.00 $320.00 $2.50 $100.00 $25.00 $1,000.00
5 2104.503 REMOVE FENCE LF 105 $11.00 $1,155.00 $10.00 $1,050.00 $10.00 $1,050.00
6 2104.504 REMOVE BITUMINOUS PAVEMENT SY 114.8 $13.59 $1,560.13 $1.00 $114.80 $10.00 $1,148.00
7 2106.507 EXCAVATION - COMMON CY 3257 $8.64 $28,140.48 $8.93 $29,085.01 $8.00 $26,056.00
8 2106.507 GRANUALR EMBANKMENT (CV)CY 161 $24.63 $3,965.43 $35.70 $5,747.70 $32.00 $5,152.00
9 2106.507 COMMON EMBANKMENT (CV)CY 3123 $2.50 $7,807.50 $8.93 $27,888.39 $8.00 $24,984.00
10 2112.519 SUBGRADE PREPARATION RD ST 18.9 $150.00 $2,835.00 $288.75 $5,457.38 $250.00 $4,725.00
11 2211.509 AGGREGATE BASE CLASS 5 TON 884 $23.25 $20,553.00 $29.40 $25,989.60 $33.00 $29,172.00
12 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (3;B) TON 398.7 $107.13 $42,712.73 $89.00 $35,484.30 $150.00 $59,805.00
13 2563.601 TRAFFIC CONTROL LS 1 $1,100.00 $1,100.00 $1,500.00 $1,500.00 $3,000.00 $3,000.00
14 2573.501 EROSION CONTROL SUPERVISOR LS 1 $1,500.00 $1,500.00 $3,000.00 $3,000.00 $3,000.00 $3,000.00
15 2573.502 STORM DRAIN INLET PROTECTION EA 2 $220.00 $440.00 $196.10 $392.20 $400.00 $800.00
16 2573.503 SILT FENCE; TYPE MS LF 4250 $3.00 $12,750.00 $2.65 $11,262.50 $3.25 $13,812.50
17 2574.507 LOAM TOPSOIL BORROW CY 520 $17.19 $8,938.80 $40.50 $21,060.00 $25.00 $13,000.00
18 2574.508 FERTILIZER TYPE 3 LB 920 $1.10 $1,012.00 $1.33 $1,223.60 $2.00 $1,840.00
19 2575.505 SEEDING AC 2.3 $1,650.00 $3,795.00 $265.00 $609.50 $1,500.00 $3,450.00
20 2575.508 HYDRAULIC BONDED FIBER MATRIX LB 8050 $1.45 $11,672.50 $2.65 $21,332.50 $2.25 $18,112.50
21 2575.608 SEED SOUTHERN BOULEVARD LB 368 $5.25 $1,932.00 $6.36 $2,340.48 $8.00 $2,944.00
$175,670.67 $236,062.16 $246,651.00
ESTIMATED
QUANTITYUNITITEM DESCRIPTION
Mn/DOT
SPEC. NO.ITEM NO.
Matt Bullock Contracting Co Inc Omann Brothers Paving Inc.Johnson Companies LLC
Page 1 of 4
BID TABULATION
CITY OF OTSEGO
2026 MEADOWS OF OTSEGO TRAIL PROJECT
Bids were opened at 2:00 p.m., August 19, 2026.
There were ten (10) bids received, as shown herein.
1 2021.501 MOBILIZATION LS 1
2 2101.505 CLEARING AC 1.55
3 2101.505 GRUBBING AC 1.55
4 2104.503 SAWING BITUMINOUS PAVEMENT - FULL DEPTH LF 40
5 2104.503 REMOVE FENCE LF 105
6 2104.504 REMOVE BITUMINOUS PAVEMENT SY 114.8
7 2106.507 EXCAVATION - COMMON CY 3257
8 2106.507 GRANUALR EMBANKMENT (CV)CY 161
9 2106.507 COMMON EMBANKMENT (CV)CY 3123
10 2112.519 SUBGRADE PREPARATION RD ST 18.9
11 2211.509 AGGREGATE BASE CLASS 5 TON 884
12 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (3;B) TON 398.7
13 2563.601 TRAFFIC CONTROL LS 1
14 2573.501 EROSION CONTROL SUPERVISOR LS 1
15 2573.502 STORM DRAIN INLET PROTECTION EA 2
16 2573.503 SILT FENCE; TYPE MS LF 4250
17 2574.507 LOAM TOPSOIL BORROW CY 520
18 2574.508 FERTILIZER TYPE 3 LB 920
19 2575.505 SEEDING AC 2.3
20 2575.508 HYDRAULIC BONDED FIBER MATRIX LB 8050
21 2575.608 SEED SOUTHERN BOULEVARD LB 368
ESTIMATED
QUANTITYUNITITEM DESCRIPTION
Mn/DOT
SPEC. NO.ITEM NO.UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION
$21,000.78 $21,000.78 $26,500.00 $26,500.00 $33,000.00 $33,000.00
$9,500.00 $14,725.00 $10,000.00 $15,500.00 $9,090.00 $14,089.50
$4,725.00 $7,323.75 $6,000.00 $9,300.00 $4,500.00 $6,975.00
$3.00 $120.00 $8.00 $320.00 $2.50 $100.00
$5.00 $525.00 $12.00 $1,260.00 $27.50 $2,887.50
$10.00 $1,148.00 $12.00 $1,377.60 $25.00 $2,870.00
$9.25 $30,127.25 $11.30 $36,804.10 $13.00 $42,341.00
$39.00 $6,279.00 $28.00 $4,508.00 $57.00 $9,177.00
$9.75 $30,449.25 $11.30 $35,289.90 $10.50 $32,791.50
$350.00 $6,615.00 $350.00 $6,615.00 $500.00 $9,450.00
$34.60 $30,586.40 $35.00 $30,940.00 $36.00 $31,824.00
$96.10 $38,315.07 $96.00 $38,275.20 $117.00 $46,647.90
$1,500.00 $1,500.00 $5,500.00 $5,500.00 $2,500.00 $2,500.00
$1,200.00 $1,200.00 $2,000.00 $2,000.00 $3,000.00 $3,000.00
$250.00 $500.00 $200.00 $400.00 $200.00 $400.00
$2.90 $12,325.00 $2.55 $10,837.50 $3.00 $12,750.00
$50.00 $26,000.00 $55.00 $28,600.00 $50.00 $26,000.00
$2.10 $1,932.00 $1.00 $920.00 $2.00 $1,840.00
$4,725.00 $10,867.50 $1,500.00 $3,450.00 $4,500.00 $10,350.00
$0.70 $5,635.00 $1.30 $10,465.00 $0.65 $5,232.50
$8.50 $3,128.00 $4.75 $1,748.00 $8.00 $2,944.00
$250,302.00 $270,610.30 $297,169.90
D&D Contracting LLCSunram Construction, Inc.KNIFE RIVER CORPORATION -
NORTH CENTRAL
Page 2 of 4
BID TABULATION
CITY OF OTSEGO
2026 MEADOWS OF OTSEGO TRAIL PROJECT
Bids were opened at 2:00 p.m., August 19, 2026.
There were ten (10) bids received, as shown herein.
1 2021.501 MOBILIZATION LS 1
2 2101.505 CLEARING AC 1.55
3 2101.505 GRUBBING AC 1.55
4 2104.503 SAWING BITUMINOUS PAVEMENT - FULL DEPTH LF 40
5 2104.503 REMOVE FENCE LF 105
6 2104.504 REMOVE BITUMINOUS PAVEMENT SY 114.8
7 2106.507 EXCAVATION - COMMON CY 3257
8 2106.507 GRANUALR EMBANKMENT (CV)CY 161
9 2106.507 COMMON EMBANKMENT (CV)CY 3123
10 2112.519 SUBGRADE PREPARATION RD ST 18.9
11 2211.509 AGGREGATE BASE CLASS 5 TON 884
12 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (3;B) TON 398.7
13 2563.601 TRAFFIC CONTROL LS 1
14 2573.501 EROSION CONTROL SUPERVISOR LS 1
15 2573.502 STORM DRAIN INLET PROTECTION EA 2
16 2573.503 SILT FENCE; TYPE MS LF 4250
17 2574.507 LOAM TOPSOIL BORROW CY 520
18 2574.508 FERTILIZER TYPE 3 LB 920
19 2575.505 SEEDING AC 2.3
20 2575.508 HYDRAULIC BONDED FIBER MATRIX LB 8050
21 2575.608 SEED SOUTHERN BOULEVARD LB 368
ESTIMATED
QUANTITYUNITITEM DESCRIPTION
Mn/DOT
SPEC. NO.ITEM NO.UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION
$52,610.00 $52,610.00 $40,000.00 $40,000.00 $20,500.00 $20,500.00
$11,460.00 $17,763.00 $12,350.00 $19,142.50 $30,000.00 $46,500.00
$6,880.00 $10,664.00 $5,850.00 $9,067.50 $4,300.00 $6,665.00
$13.00 $520.00 $15.00 $600.00 $2.63 $105.20
$13.50 $1,417.50 $12.00 $1,260.00 $15.00 $1,575.00
$11.00 $1,262.80 $5.00 $574.00 $15.00 $1,722.00
$17.05 $55,531.85 $20.00 $65,140.00 $42.11 $137,152.27
$39.44 $6,349.84 $35.00 $5,635.00 $16.00 $2,576.00
$10.50 $32,791.50 $20.00 $62,460.00 $9.00 $28,107.00
$272.00 $5,140.80 $150.00 $2,835.00 $200.00 $3,780.00
$35.26 $31,169.84 $36.00 $31,824.00 $55.22 $48,814.48
$133.00 $53,027.10 $128.00 $51,033.60 $102.59 $40,902.63
$0.01 $0.01 $1,200.00 $1,200.00 $1,050.00 $1,050.00
$2,710.00 $2,710.00 $1.00 $1.00 $5,000.00 $5,000.00
$267.00 $534.00 $225.00 $450.00 $120.00 $240.00
$3.50 $14,875.00 $4.50 $19,125.00 $2.25 $9,562.50
$28.28 $14,705.60 $30.00 $15,600.00 $49.09 $25,526.80
$2.20 $2,024.00 $1.25 $1,150.00 $0.65 $598.00
$287.00 $660.10 $2,350.00 $5,405.00 $500.00 $1,150.00
$2.20 $17,710.00 $1.75 $14,087.50 $3.00 $24,150.00
$6.40 $2,355.20 $6.00 $2,208.00 $5.46 $2,009.28
$323,822.14 $348,798.10 $407,686.16
New Look Contracting, Inc.Husky ConstructionVeit & Company, Inc.
Page 3 of 4
BID TABULATION
CITY OF OTSEGO
2026 MEADOWS OF OTSEGO TRAIL PROJECT
Bids were opened at 2:00 p.m., August 19, 2026.
There were ten (10) bids received, as shown herein.
1 2021.501 MOBILIZATION LS 1
2 2101.505 CLEARING AC 1.55
3 2101.505 GRUBBING AC 1.55
4 2104.503 SAWING BITUMINOUS PAVEMENT - FULL DEPTH LF 40
5 2104.503 REMOVE FENCE LF 105
6 2104.504 REMOVE BITUMINOUS PAVEMENT SY 114.8
7 2106.507 EXCAVATION - COMMON CY 3257
8 2106.507 GRANUALR EMBANKMENT (CV)CY 161
9 2106.507 COMMON EMBANKMENT (CV)CY 3123
10 2112.519 SUBGRADE PREPARATION RD ST 18.9
11 2211.509 AGGREGATE BASE CLASS 5 TON 884
12 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (3;B) TON 398.7
13 2563.601 TRAFFIC CONTROL LS 1
14 2573.501 EROSION CONTROL SUPERVISOR LS 1
15 2573.502 STORM DRAIN INLET PROTECTION EA 2
16 2573.503 SILT FENCE; TYPE MS LF 4250
17 2574.507 LOAM TOPSOIL BORROW CY 520
18 2574.508 FERTILIZER TYPE 3 LB 920
19 2575.505 SEEDING AC 2.3
20 2575.508 HYDRAULIC BONDED FIBER MATRIX LB 8050
21 2575.608 SEED SOUTHERN BOULEVARD LB 368
ESTIMATED
QUANTITYUNITITEM DESCRIPTION
Mn/DOT
SPEC. NO.ITEM NO.UNIT PRICE EXTENSION
$48,000.00 $48,000.00
$10,100.00 $15,655.00
$6,060.00 $9,393.00
$12.40 $496.00
$16.90 $1,774.50
$16.50 $1,894.20
$37.00 $120,509.00
$50.00 $8,050.00
$44.50 $138,973.50
$346.00 $6,539.40
$38.30 $33,857.20
$104.00 $41,464.80
$1,010.00 $1,010.00
$1,350.00 $1,350.00
$202.00 $404.00
$2.60 $11,050.00
$66.20 $34,424.00
$1.00 $920.00
$1,520.00 $3,496.00
$1.30 $10,465.00
$4.80 $1,766.40
$491,492.00
Park Construction Company
Page 4 of 4
1
CITY OF OTSEGO
COUNTY OF WRIGHT
STATE OF MINNESOTA
RESOLUTION NO: 2026-73
ACCEPTING BIDS AND AWARDING CONTRACT
WHEREAS, pursuant to an advertisement for bids for the construction of the 2026 Meadows of Otsego Trail Project, City
Project No. 26-03, bids were received, opened on August 19, 2026, and tabulated according to law, and the following bids
were received complying with the advertisement; and
Contractor Total Base Bid
1. Matt Bullock Contracting Co, Inc. $175,670.67
2. Omann Brothers Paving, Inc. $236,062.16
3. Johnson Companies LLC $246,651.00
4. Sunram Construction, Inc. $250,302.00
5. Knife River Corporation – North Central $270,610.30
6. D&D Contracting, LLC $297,169.90
7. Veit & Company, Inc. $323,822.14
8. New Look Contracting, Inc. $348,798.10
9. Husky Construction $407,686.16
10. Park Construction Company $491,492.00
WHEREAS, it appears that Matt Bullock Contracting Co, Inc., of St. Michael, Minnesota is the lowest responsible bidder.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF OTSEGO, MINNESOTA:
1. The Mayor and City Clerk are hereby authorized and directed to enter into a contract with Matt Bullock Contracting
Co, Inc., of St. Michael, Minnesota in the name of the City of Otsego for the 2026 Meadows of Otsego Trail Project,
City Project No. 26-03, according to the plans and specifications therefore approved by the City Council and on file in
the office of the City Clerk.
2. The City Clerk is hereby authorized and directed to return forthwith to all bidders the bid bond made with their bids,
except that the bid bond of the successful bidder and the next lowest bidder shall be retained until a contract has
been signed.
2
ADOPTED by the Otsego City Council this 24th day of August, 2026.
MOTION BY:
SECONDED BY:
IN FAVOR:
OPPOSED: