Item 1. 2021-2023 Street Renewal Summary Funding Options2021-2031 Street Renewal Summary Funding Options Total Estimate Local Street Renewal Costs for next 11 years = $ 6,654,701.29 (with inflation) $ 5,357,030.17 2021 dollars Total Estimate Local Street in Otsego = 96.34 miles 1,517,086 sq.yds Total Non-MSA (local) street to be renewed over next 11 years = 15.65 miles 225,461 sq.yds Cost to complete pavement life cycle (50 years @ 2021 dollars) = 96.34 / 15.65 *$5,357,030 = $ 32,977,797.61 Local Streets Only Rural Urban 2020 Overlay Average $13.94 per SY $13.47 per SY 2020 Reclaim Average $22.60 per SY $38.95 per SY 2020 Reconstruct Average $38.58 per SY $55.81 per SY Front Footage (ft) Portion of Road responsible for (Sq.Yds) Large Lot (Rural) Average = 250 333.3 Urban Lot Average = 90 120.0 Average Per Lot Assessment (assumes 50% City funded) for various project types Rural Urban Overlay $2,323.48 $808.05 Reclaim $3,767.16 $2,336.70 Reconstruction $6,430.62 $3,348.53