Item 3.10 Wellhouse No 4 Water Treatment Plant Amendment No 2 to Engineering Agreement
Request for
City Council Action
DEPARTMENT INFORMATION
ORIGINATING DEPARTMENT REQUESTOR: MEETING DATE:
Utilities Utility Manager Neidermeier February 9, 2026
PRESENTER(s) REVIEWED BY: ITEM #:
Consent
AE2S Engineer Hanson
City Administrator/Finance Director Flaherty
3.10 – Wellhouse 4 WTP
STRATEGIC VISION
MEETS: THE CITY OF OTSEGO:
Is a strong organization that is committed to leading the community through innovative communication.
X Has proactively expanded infrastructure to responsibly provide core services.
Is committed to delivery of quality emergency service responsive to community needs and expectations in a
cost-effective manner.
Is a social community with diverse housing, service options, and employment opportunities.
Is a distinctive, connected community known for its beauty and natural surroundings.
AGENDA ITEM DETAILS
RECOMMENDATION:
City Staff is recommending City Council approve an amendment to the AE2S professional services contract for the
Wellhouse No. 4 Treatment Improvements project.
ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED?
Yes No
BACKGROUND/JUSTIFICATION:
The City of Otsego has an existing professional services agreement with AE2S to provide engineering services for the
Wellhouse No. 4 Water Treatment Improvements project. The original agreement included engineering design, bidding,
and construction phase services based on assumptions of part-time construction support and limited on-site
observation.
Since the start of construction, project conditions have required a greater level and duration of engineering construction
administration and on-site observation than originally anticipated. AE2S has provided increased on-site representation,
contractor coordination, submittal and RFI review, QA/QC oversight, bi-weekly progress meetings, and construction
documentation review to ensure construction accuracy and compliance. Construction schedule delays, increased field
coordination needs, and a City-approved 11-day schedule extension have further increased the required level of effort.
As a result, AE2S has requested an amendment to the Owner–Engineer Agreement to address additional construction
administration, resident project representative (RPR) services, and associated support beyond the original scope. The
amendment also includes additional plumbing design services required to address code changes identified during
construction.
The requested amendment totals $73,550.00. Approval of this amendment will increase the total not-to-exceed amount
of the professional services agreement with AE2S to $1,166,250.00.
AE2S Agreement Amount
Original Agreement Amount + Construction & IC Services: $ 1,092,700.00
This Amendment Amount: $ 73,550.00
Adjusted Agreement Amount: $ 1,166,250.00
Construction Contract Amount
Original Contract Amount: $ 6,840,000.00
Net Change Orders to Date: $ 139,459.86
Adjusted Contract Amount: $ 6,979,459.86
When viewed together, the construction change orders and amended engineering services agreement currently
increase the project costs by $213,009.86, which represents approximately 62% of the project contingency in the
financing package. With this month’s pay application from Market & Johnson, the construction contract is
approximately 83.0% complete, and only limited additional changes are anticipated as the project progresses toward
commissioning and startup.
The proposal was presented to the Public Works Subcommittee on January 21, 2026. The City Attorney has reviewed the
proposed amendment. Staff recommend approval of the amendment to allow AE2S to continue providing construction
support services through project completion.
SUPPORTING DOCUMENTS ATTACHED:
• Amendment No. 2 to Owner-Engineer Agreement
POSSIBLE MOTION
PLEASE WORD MOTION AS YOU WOULD LIKE IT TO APPEAR IN THE MINUTES:
Motion to approve “Amendment to Owner-Engineering Agreement, Amendment No. 2” – a professional services
contract amendment in the amount of $73,550.00 with Advanced Engineering and Environmental Services, LLC.
BUDGET INFORMATION
FUNDING: BUDGETED:
Fund 601 – Drinking Water Utility
Yes
Amendment No. 2
Page 1
AE2S PROJECT NO.: P05409-2020-010
AMENDMENT TO OWNER-ENGINEER AGREEMENT
Amendment No. 2
Effective Date of Owner-Engineer
Agreement:
February 13, 2023
Owner: City of Otsego
Engineer: Advanced Engineering and Environmental Services, LLC
Specific Project: Wellhouse No. 4 Treatment Improvements
Nature of Amendment:
X Modifications of services performed by Engineer
X Modification of payment to Engineer
X Modifications to time(s) for rendering services
Description of Modifications:
a. The Scope of Services currently authorized to be performed by Engineer in accordance with the
Agreement and previous amendments, if any, is modified as follows:
• Additional on-site observation (RPR) services beyond the originally scoped part-time effort.
• Additional plumbing design services required to address code changes.
• Additional construction administration and RPR services associated with an 11-day construction
schedule extension resulting from approved change orders.
b. For the modifications of services set forth above, Owner shall pay Engineer the following additional
compensation on an hourly basis, not to exceed $73,550.00 without written authorization from the
Owner.
c. The schedule for rendering services under this Amendment is modified as follows:
• 11-day extension from the original 18-month substantial completion date.
Agreement Summary:
Original agreement amount: $ 390,200.00
Net change for prior amendments: $ 702,500.00
This amendment amount: $ 73,550.00
Adjusted Agreement amount: $ 1,166,250.00
Owner and Engineer hereby agree to modify the above-referenced Agreement as set forth in this
Amendment. All provisions of the Agreement not modified by this or previous Amendments remain in
effect.
Amendment No. 2
Page 2
The Effective Date of this Amendment is February 9, 2026.
OWNER: ENGINEER:
City of Otsego Advanced Engineering and Environmental Services,
LLC
By: By: {{__evi__Signer1_es_:signer1:signature}}
Date: Date: {{__evi__Dte1_es_:signer1:date:required}}
Name: Name: Justin Klabo
Title: Title: Operations Manager
Amendment No. 2
Page 3
ADVANCED ENGINEERING AND ENVIRONMENTAL SERVICES, LLC
2026 HOURLY FEE AND EXPENSE SCHEDULE
Labor Rates*
Administrative 1 $73.00
Administrative 2 $88.00
Administrative 3 $103.00
Communications Specialist 1 $117.00
Communications Specialist 2 $137.00
Communications Specialist 3 $158.00
Communications Specialist 4 $190.00
Communications Specialist 5 $210.00
Construction Services 1 $140.00
Construction Services 2 $171.00
Construction Services 3 $190.00
Construction Services 4 $211.00
Construction Services 5 $232.00
Engineering Assistant 1 $94.00
Engineering Assistant 2 $111.00
Engineering Assistant 3 $140.00
Engineer 1 $152.00
Engineer 2 $182.00
Engineer 3 $213.00
Engineer 4 $246.00
Engineer 5 $264.00
Engineer 6 $279.00
Engineering Technician 1 $93.00
Engineering Technician 2 $117.00
Engineering Technician 3 $141.00
Engineering Technician 4 $158.00
Engineering Technician 5 $181.00
Financial Analyst 1 $126.00
Financial Analyst 2 $142.00
Financial Analyst 3 $171.00
Financial Analyst 4 $187.00
Financial Analyst 5 $209.00
GIS Specialist 1 $117.00
GIS Specialist 2 $142.00
GIS Specialist 3 $168.00
GIS Specialist 4 $188.00
GIS Specialist 5 $210.00
I&C Assistant 1 $112.00
I&C Assistant 2 $139.00
I&C 1 $166.00
I&C 2 $196.00
I&C 3 $221.00
I&C 4 $234.00
I&C 5 $246.00
IT 1 $145.00
IT 2 $196.00
IT 3 $241.00
Land Surveyor Assistant $107.00
Land Surveyor 1 $129.00
Land Surveyor 2 $156.00
Land Surveyor 3 $175.00
Land Surveyor 4 $193.00
Land Surveyor 5 $213.00
Operations Specialist 1 $112.00
Operations Specialist 2 $140.00
Operations Specialist 3 $173.00
Operations Specialist 4 $198.00
Operations Specialist 5 $222.00
Project Coordinator 1 $130.00
Project Coordinator 2 $145.00
Project Coordinator 3 $162.00
Project Coordinator 4 $178.00
Project Coordinator 5 $201.00
Project Manager 1 $229.00
Project Manager 2 $251.00
Project Manager 3 $269.00
Project Manager 4 $284.00
Project Manager 5 $303.00
Project Manager 6 $317.00
Sr. Designer 1 $199.00
Sr. Designer 2 $221.00
Sr. Designer 3 $238.00
Sr. Financial Analyst 1 $236.00
Sr. Financial Analyst 2 $257.00
Sr. Financial Analyst 3 $279.00
Technical Expert 1 $361.00
Technical Expert 2 Negotiable
Amendment No. 2
Page 4
Reimbursable Expense Rates
Transportation $0.83/mile
Survey Vehicle $1.05/mile
Laser Printouts/Photocopies $0.30/copy
Plotter Printouts $1.00/s.f.
UAS - Photo/Video Grade $100.00/day
UAS/USV – Survey $50.00/hour
Total Station – Robotic $35.00/hour
Mapping GPS $60.00/day
Fast Static/RTK GPS $50.00/hour
All-Terrain Vehicle/Boat $100.00/day
Cellular Modem $75.00/month
Web Hosting $26.00/month
Legal Services Reimbursement $302.00/hour
Outside Services cost * 1.15
Geotechnical Services cost * 1.30
Out of Pocket Expenses cost * 1.15
Rental Car cost * 1.20
Project Specific Equipment Negotiable
* Position titles are for labor rate grade purposes only.
These rates are subject to adjustment each year on January 1.