Loading...
Item 3.21 2026 Mill and Overlay Project Approve Plans and Specifications and Order Advertisment of Bids Request for City Council Action DEPARTMENT INFORMATION ORIGINATING DEPARTMENT REQUESTOR: MEETING DATE: Public Works City Engineer Wagner January 26, 2026 PRESENTER(s) REVIEWED BY: ITEM #: Consent City Administrator/Finance Director Flaherty 3.21 – Mill & Overlay Project STRATEGIC VISION MEETS: THE CITY OF OTSEGO: Is a strong organization that is committed to leading the community through innovative communication. X Has proactively expanded infrastructure to responsibly provide core services. Is committed to delivery of quality emergency service responsive to community needs and expectations in a cost-effective manner. Is a social community with diverse housing, service options, and employment opportunities. Is a distinctive, connected community known for its beauty and natural surroundings. AGENDA ITEM DETAILS RECOMMENDATION: City staff recommend the City Council approval plans and specifications and authorize the bid process. ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED? No No BACKGROUND/JUSTIFICATION: Plans and specifications have been completed for the 2026 Mill & Overlay Project. The attached project maps indicate the streets included within this project, which have 2025 PCI Ratings between 54-60 indicating the need for the project. The Capital Improvement Plan (CIP) includes $1,778,407 to fund this project, with the current engineer estimate of project costs to be $1,619,077. Pending approval, City staff would anticipate bid results being presented to the City Council in late February or early March. The Public Works Subcommittee reviewed this item at their January 21, 2026, meeting and recommended consideration of approval by the City Council. SUPPORTING DOCUMENTS ATTACHED: • Project Maps • Engineer’s Estimate POSSIBLE MOTION PLEASE WORD MOTION AS YOU WOULD LIKE IT TO APPEAR IN THE MINUTES: Motion to approve the Plans and Specifications and Order Advertisement for Bids for the 2026 Mill & Overlay Project. BUDGET INFORMATION FUNDING: BUDGETED: Fund 201 - Pavement Management Yes Engineer's Estimate City of Otsego 2026 Mill and Overlay and Overlay ProjectSCHEDULE A - MILL & OVERLAY Item No. MnDOT Spec Description Estimated Quantity Unit Unit Price Extension 1 2021.5 MOBILIZATION 1 LS 32,501$ 32,501$ 2 2357.51 BITUMINOUS MATERIAL FOR TACK COAT 6251 GAL 3.50$ 21,878$ 3 2232.5 MILL BITUMINOUS SURFACE 125016 SY 1.50$ 187,525$ 4 2360.51 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT 10799 TON 80.00$ 863,953$ 5 2563.6 TRAFFIC CONTROL 1 LS 10,000.00$ 10,000$ 1,115,856$ 5%55,793$ 5%55,793$ 1,227,441$ SCHEDULE B - Overlay Item No. MnDOT Spec Description Estimated Quantity Unit Unit Price Extension 1 2021.5 MOBILIZATION 1 LS 10,370$ 10,370$ 2 2221.51 SHOULDER BASE SALVAGED MILLINGS 382 TON 35.00$ 13,360$ 3 2357.51 BITUMINOUS MATERIAL FOR TACK COAT 2288 GAL 3.50$ 8,009$ 4 2360.51 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT 3954 TON 80.00$ 316,293$ 5 2563.6 TRAFFIC CONTROL 1 LS 8,000.00$ 8,000$ 356,032$ 5%8,901$ 5%8,901$ 391,636$ 1,619,077$ Engineering and Construction Contingency Total Estimated Construction Cost TOTAL COST Total Estimated Construction Cost TOTAL COST TOTAL COST BOTH SCHEDULES Engineering and Construction Contingency