Loading...
Item 3.13 Approve Pay Application No. 1 and Change Order No. 1 for the 80th Street Trail Imrpovement Project Request for City Council Action DEPARTMENT INFORMATION ORIGINATING DEPARTMENT REQUESTOR: MEETING DATE: Public Works City Engineer Wagner October 13, 2025 PRESENTER(s) REVIEWED BY: ITEM #: Consent City Administrator/Finance Director Flaherty 3.13 – Pay Application for 80th Street Trail Project STRATEGIC VISION MEETS: THE CITY OF OTSEGO: Is a strong organization that is committed to leading the community through innovative communication. X Has proactively expanded infrastructure to responsibly provide core services. Is committed to delivery of quality emergency service responsive to community needs and expectations in a cost-effective manner. Is a social community with diverse housing, service options, and employment opportunities. X Is a distinctive, connected community known for its beauty and natural surroundings. AGENDA ITEM DETAILS RECOMMENDATION: City staff are recommending City Council approval of Pay Application #1 and Change Order #1 for the 80th Street Trail Improvement Project. ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED? No No BACKGROUND/JUSTIFICATION: This pay application is for mobilization, clearing and grubbing, removals, sawing bituminous pavement, common embankment, aggregate base, culvert and sewer, silt fence, and other work. Items remaining include wearing course mixture, concrete walk and driveway, curb and gutter, and seeding. Change Order #1 includes three items. Item 1 is removal of deteriorated concrete driveway where the trail crosses. Item 2 is replacement of discovered draintile compromised by trail. Item 3 is removal of large tree that fill slope is covering the trunk to a depth of 2’. In accordance with Minnesota Statute, the City is withholding the maximum of 5% retainage of work completed, which amounts to $8,918.10 at this time. SUPPORTING DOCUMENTS ATTACHED: • Pay Application #1 • Change Order #1 POSSIBLE MOTION PLEASE WORD MOTION AS YOU WOULD LIKE IT TO APPEAR IN THE MINUTES: Motion to approve Change Order #1 and Pay Application #1 to New Look Contracting, Inc. in the amount of $169,443.90 for the 80th Street Trail Improvement Project. BUDGET INFORMATION FUNDING: BUDGETED: Fund 203 – Park Development Yes PAY ESTIMATE #1 City of Otsego - 2025 80th Street Trail Improvement Project Through October 7, 2025 ITEM NO.ITEM DESCRIPTION ESTIMATED QUANTITY UNIT CONTRACT UNIT PRICE CONTRACT AMOUNT USED TO DATE EXTENSION 1 MOBILIZATION 1 LS 21,000.00$ $ 21,000.00 0.5 10,500.00$ 2 CLEARING AND GRUBBING 1 LS 1,250.00$ $ 1,250.00 1 1,250.00$ 3 SALVAGE SIGN 1 EA 115.00$ $ 115.00 -$ 4 REMOVE PIPE CULVERTS 12 LF 50.00$ $ 600.00 12 600.00$ 5 SAWING BITUMINOUS PAVEMENT (FULL DEPTH)241 LF 5.00$ $ 1,205.00 241 1,205.00$ 6 REMOVE CURB AND GUTTER 4 SY 225.00$ $ 900.00 4 900.00$ 7 REMOVE BITUMINOUS PAVEMENT 204 SY 10.00$ $ 2,040.00 204 2,040.00$ 8 EXCAVATION - COMMON (CV)3908 CY 8.50$ $ 33,218.00 3908 33,218.00$ 1 COMMON EMBANKMENT (CV)5881 CY 16.00$ $ 94,096.00 3500 56,000.00$ 10 SUBGRADE PREPARATION 19 RDST 225.00$ $ 4,275.00 19 4,275.00$ 11 AGGREGATE BASE CLASS 5 814 TON 30.00$ $ 24,420.00 869 26,070.00$ 12 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 387 TON 110.00$ $ 42,570.00 -$ 13 12" RC PIPE APRON 1 EA 2,550.00$ $ 2,550.00 1 2,550.00$ 14 12" RC PIPE CULVERT CLASS V 44 LF 108.00$ $ 4,752.00 44 4,752.00$ 15 12" RC PIPE SEWER CLASS V 23 LF 104.00$ $ 2,392.00 23 2,392.00$ 16 CONNECT TO EXISTING STORM SEWER 2 EA 1,550.00$ $ 3,100.00 2 3,100.00$ 17 CASTING ASSEMBLY 2 EA 825.00$ $ 1,650.00 -$ 18 CONSTRUCT DRAINAGE STRUCTURE DESIGN 48-4020 2 EA 4,675.00$ $ 9,350.00 2 9,350.00$ 19 6" CONCRETE WALK 252 SF 10.00$ $ 2,520.00 -$ 20 6" CONCRETE DRIVEWAY PAVEMENT 9 SY 170.00$ $ 1,530.00 -$ 21 B612 CONCRETE CURB AND GUTTER 44 LF 30.00$ $ 1,320.00 -$ 22 TRUNCATED DOMES 67 SF 60.00$ $ 4,020.00 -$ 23 TRAFFIC CONTROL 1 LS 1,350.00$ $ 1,350.00 0.5 675.00$ 24 STORM DRAIN INLET PROTECTION 3 EA 235.00$ $ 705.00 2 470.00$ 25 CULVERT END CONTROLS 1 EA 235.00$ $ 235.00 -$ 26 SILT FENCE TYPE MS 1208 LF 4.00$ $ 4,832.00 1103 4,412.00$ 27 SEDIMENT CONTROL LOG TYPE STRAW 739 LF 4.00$ $ 2,956.00 841 3,364.00$ 28 FERTILIZER TYPE 1 240 LBS 2.00$ $ 480.00 -$ 29 SEEDING 1 ACRE 2,000.00$ $ 1,600.00 -$ 30 HYDRAULIC BONDED FIBER MATRIX 2800 LBS 2.00$ $ 5,600.00 -$ 31 SOUTHERN BOULEVARD SEED MIXTURE 128 LBS 8.00$ $ 1,024.00 -$ 277,655.00$ 167,123.00$ Base Bid Total Base Bid Page 1 PAY ESTIMATE #1 City of Otsego - 2025 80th Street Trail Improvement Project ITEM NO.ITEM DESCRIPTION ESTIMATED QUANTITY UNIT CONTRACT UNIT PRICE CONTRACT AMOUNT USED TO DATE EXTENSION 1 CO 1 REMOVE CONCRETE DRIVEWAY 156 SF 3.50$ $ 546.00 156 546.00$ 2 CO 1 DRAINTILE (PER REVISED PLAN)196 LS 39.25$ $ 7,693.00 196 7,693.00$ 3 CO 1 36” MAPLE TREE CLEAR & GRUB 1 EA 3,000.00$ $ 3,000.00 1 3,000.00$ 11,239.00$ 11,239.00$ 288,894.00$ 178,362.00$ Total Change Orders Change Order Total Base Bid + Change Order Page 2