Item 3.8 West WWTF Improvements Project Change Orders Request for City Council Action DEPARTMENT INFORMATION ORIGINATING DEPARTMENT REQUESTOR: MEETING DATE: Utilities Utility Manager Neidermeier July 28, 2025 PRESENTER(s) REVIEWED BY: ITEM #: Consent AE2S Engineer Schaefer Assistant City Administrator/Human Resources Hille 3.8 – West WWTF Project Change Order Proposals STRATEGIC VISION MEETS: THE CITY OF OTSEGO: Is a strong organization that is committed to leading the community through innovative communication. X Has proactively expanded infrastructure to responsibly provide core services. Is committed to delivery of quality emergency service responsive to community needs and expectations in a cost-effective manner. Is a social community with diverse housing, service options, and employment opportunities. Is a distinctive, connected community known for its beauty and natural surroundings. AGENDA ITEM DETAILS RECOMMENDATION: City Staff is recommending that the City Council approve change orders for the West WWTF project. ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED? No No BACKGROUND/JUSTIFICATION: A package of Change Order Proposals for the West WWTF project were reviewed with the Public Works Subcommittee (PWSC) on July 16, 2025. The following table is a summary of the change orders that were recommended to forward for consideration by the full Council. CPR 74 UV Building Extra Work $10,182 CPR 76 Additional Grating in PTB $14,981 CPR 77 Add Baffle Walls in PTB tanks $30,051 CPR 78 Miscellaneous Changes Group A – Process Piping and Channels $23,457 CPR 79 Miscellaneous Changes Group B – Earthwork and Sitework $13,723 CPR 80 Miscellaneous Changes Group C – Instrumentation $3,009 CPR 81 Miscellaneous Changes Group D – Buildings/Structural $3,203 CPR 82 Natural Gas Use Credit ($15,927) The change orders represent various justifications ranging from necessary modifications to “pass-through” utility costs to complete the project. Note that the #77 did not have final pricing on July 16, and the cost increase was due to shipping. The proposed net increase in project cost of $83,129 represents 0.245% of the bid cost and would bring the total change order plus authorized direct purchase items amount to a net increase to 5.30% for the project. SUPPORTING DOCUMENTS ATTACHED: • Detailed proposals for change orders 74 and 76 through 82 POSSIBLE MOTION PLEASE WORD MOTION AS YOU WOULD LIKE IT TO APPEAR IN THE MINUTES: Motion to approve Change Order Proposals #74 and #76 to #82 as indicated in the table above in the amount of $83,129 to Rice Lake Construction Group for the West WWTF Project. BUDGET INFORMATION FUNDING: BUDGETED: Fund 602 – Sanitary Sewer Utility Yes June 4, 2025 AE2S 6901 East Fish Lake Rd. Suite 184 Maple Grove, MN 55369-5457 ATTN: Scott Schaefer, PE Re: Otsego West WWTF Improvements Phase 1 RLCG Project No. 2215 Change Order Proposal #: 074 – UV Building Extra Work Scott, It was noted in the response to RFI073 that Rice Lake was to install a C-Channel above the new opening for the overhead door, demo out some compressed air piping, and form a trench drain and sump into the concrete infill. Also included was some additional electrical work for a sensor located in the Cascade Aeration. The total cost to complete this extra work was $10,182.00. Attached is a breakout of the costs. Please let me know if you have any questions. Sincerely, Rice Lake Construction Group Matt Perpich Project Manager 2215 Otsego West WWTF Improvements Phase 1 22360 County Road 12, PO Box 517 6/4/2025 Deerwood, MN 56444 74 HOURS $ RATE TOTAL RATE TOTAL RLCG Labor - Trench Drain Work 26.00 HR 26.00 109.00$ $2,834.00 -$ $0.00 -$ -$ 2,834.00$ RLCG Labor - C-Channel/Demo 12.00 HR 12.00 109.00$ $1,308.00 -$ $0.00 -$ -$ 1,308.00$ RLCG Material 1.00 LS -$ $0.00 550.00$ $550.00 -$ -$ 550.00$ RLCG Equipment LS -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Killmer 1.00 LS -$ $0.00 -$ $0.00 4,179.45$ -$ 4,179.45$ -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Misc. Small Tools and Mat'l 5% of Labor 1.00 ea 5.00%207.10$ Sales Tax 1.00 ea 7.375%40.56$ Totals 38.00 4,142.00$ 550.00$ 4,179.45$ -$ 9,119.11$ Rice Lake Mark-up on Subs (5%)208.97$ Rice Lake Mark-up on Labor, Material, and Equipment (15%)703.80$ Bond Cost (1.5%)150.48$ Total Change Order Proposal Request 10,182.00$ Days Requested 0 RLCG PROJECT #: PROJECT NAME: DATE: COP: CHANGE ORDER PROPOSAL MATERIAL SUBCONTRACTOR TOTAL EQUIPMENT TOTAL LINE TOTALDESCRIPTIONQTYUNITLABOR An Equal Opportunity Employer May 29, 2025 Mr. Matt Perpich Rice Lake Construction Group Re: Otsego West WWTP Dear Matt, Killmer Electric Company proposes to the following change to our contract for the subject project: Change Request – RFI 73 – HACH Probe Wiring Costs below to provide and install Conduit and wiring from UV building to Cascade Aeration and install HAV probe and transmitter as furnished by City. RFI 73 - Hach Probe and Transmitter wired back to UV control panel and power QTY Mat unit Mat total Labor unit Total labor Panelboard and SCP Terms/test 1 6.5 $6.50 1.5 1.5 Install Hach Transmitter and Probe FBO 1 125 $125.00 4 4 Exterior Penetrations 2 8 $16.00 1 2 3/4" Rigid 170 4.25 $722.50 0.065 11.05 12awg THHN 285 0.245 $69.83 0.0065 1.8525 16awg 2/c TSP 100 0.65 $65.00 0.012 1.2 Totals $1,004.83 21.6025 Tax $80.39 118 / hour $2,549.10 $1,085.21 $2,549.10 $3,634.31 15.00% $545.15 $4,179.45 Total Cost Add: $4,179.45 Please call with any questions or comments. Regards, Matthew Pettit Project Manager Priorities: TO: Scott Schaefer, PE Priority (1-5) 2 1 = 8 hours 4 = 5 days Received: 2 = 2 days 5 = 2 weeks Answered: 3 = 3 days cc: Superintendent, RLCG ____________________ ___________________ ___________________ RFI# 073 REQUEST FOR INFORMATION Subject: UV Overhead Door Location Location: UV Owner: City of Otsego Routing: Project: Otsego, MN WWTP Other: Drawing No: UV A201 and UV E102 Spec. DIV 08 and DIV 26 REQUEST The proposed location of the overhead door in the UV building appears to conflict with existing equipment and piping in the UV building. Note 3 on UV E102 states that the electrical contractor must disconnect the existing compressor and all the associated cable and conduit back to the source. There is additional water/air piping and conduit inside of the wall that would need to be removed in this location. If Rice Lake is to install the overhead door in this location, there will be associated costs with the extra demo work. Please advise if Rice Lake should install the door in the location shown on the plans, or if the opening should be moved to a different location in the building. See attached photo of extra pipe and conduit in this area. Name: Matt Perpich Company: Rice Lake Construction Date: January 16, 2024 RESPONSE Name: Date: T T MS T (1) (3) 18" 1 (1)(1) 18" 1 (1) (3)4 WAP-1025 (1)(3) 12 WAP-102A8 (1)(1) 18" 1 WAP-1085 (1) (3) 18" 1 (1) (3)4 (3) (1)4 VSS-73 (1) (1) 60" 1 (1) (2) 72" 1 (1) (2) 72" 1 (1) (1) 18" 1 (1) (1) 18" 1 (1) (3) 18" 1 WAP-102B5 RE CR 2 REES DS CR 105 103 106109A111 113 112 102B 115 114A 109AB 101 102A 108 110B 110A SHOP 115 ELECTRICAL 114 GARAGE 120 TOILET 112 TOILET (ADA) 113 LOCKERS 111 MECHANICAL 109 IT 109A VESTIBULE 101 SCADA 102A OFFICE 105 FILE ROOM 104 OFFICE 103 TRAINING 108 BREAK ROOM 110 DAC-101 RE DSDS 2 DAC-102A C R RE DSES 2DAC-103 CR P PANIC DS ES RE 2DAC-105 2 DAC-110C VSS-6 3 (1) (3)4 (1) (3)4 WAP-115 5 110C (1) (2) 72" 1 (3)(1) 18" 1 (1) (3) 18" 1 CR (1) (2) 72" 1 (1) (1) 18" 1 (1)(1) 72" 1 (1)(1) 18" 1 (1) (2) 72" 1 NWP1 IC6 JANITOR 107 TOILET 106 CORRIDOR 102B (1) (2) 72" 1 (1) (1) 18" 1 H7 FAE-115A S7 FAE-114A H7 FAE-115B F F FAHS-115 7 FAPS-115 7 S7 FAE-110A S7 FAE-110B F FAHS-1107 F FAPS-110 7 FFAHS-102B27 F FAPS-102B 7 SFAS-1137 SFAS-1127 FFAHS-1117 F FAHS-102B17 (1)(2) 60" 11 F FAHS-108 7 (1) (2) 72" 1 S 8 FAE-AHU1R S7 FAE-109 FFAHS-1097 FAE-AHU1S S8 F FAHS-102A27 S 7 FAE-109A2 FACP-0019 F FAHS-102A1 7 F FAPS-102A 7 FARA-00110 F FAHS-102A3 7 (1)(3) 12 S 7 FAE-109A1 PTD DSDSPTDPSPS TO PTD-102A TO PTD-101~~2 CONSTRUCTION NOTES • CONTRACTOR TO FURNISH AND INSTALL WALL MOUNTED RJ45 DATA JACKS. QUANTITY/TYPE AND HEIGHT AS INDICATED. • DOOR SECURITY EQUIPMENT. SEE ACCESS CONTROL SYSTEM RISER DIAGRAM, NETWORK DIAGRAM, AND CABLE AND CONDUIT SCHEDULE FOR ALL CIRCUITING REQUIREMENTS AS WELL AS SCOPE OF SUPPLY RESPONSIBILITIES. • ELECTRICAL CONTRACTOR TO PROVIDE FLUSH MOUNTED ABOVE COUNTER RJ45 DATA JACK INTEGRAL TO SCADA DESK. COORDINATE BOX LOCATIONS, ELECTRICAL CHASE AND FEED POINT WITH GENERAL CONTRACTOR. • CONTRACTOR TO FURNISH AND INSTALL FLOOR MOUNTED RJ45 DATA JACKS IN COMMON FLOOR BOX WITH POWER (SEE LGPM SHEETS). QUANTITY/TYPE AS INDICATED. 1 2 3 • WIRELESS ACCESS POINT (40 95 13) FURNISHED BY SYSTEMS INTEGRATOR AND INSTALLED BY ELECTRICAL CONTRACTOR. PROVIDE CAT6 CABLE WITH RJ45 JACK AS SHOWN ON NETWORK DIAGRAM AND DEFINED IN THE CABLE AND CONDUIT SCHEDULE. • VIDEO CAPABLE INTERCOM CALL BOX. SEE ACCESS CONTROL RISER DIAGRAM FOR ADDITIONAL REQUIREMENTS. • FIRE ALARM DEVICE FURNISHED BY DIVISION 28, INSTALLED BY DIVISION 26. CIRCUIT AND CONNECT PER RESPECTIVE FIRE ALARM RISER AND PER MANUFACTURER'S RECOMMENDATIONS. SEE (28 30 00) FOR ADDITIONAL REQUIREMENTS. • DUCT MOUNTED FIRE ALARM DEVICE FURNISHED BY DIVISION 28, INSTALLED BY DIVISION 26. CIRCUIT AND CONNECT PER RESPECTIVE FIRE ALARM RISER AND PER MANUFACTURER'S RECOMMENDATIONS. COORDINATE EXACT INSTALLATION LOCATION WITH MECHANICAL CONTRACTOR. SEE (28 30 00) AND 'SD' DRAWINGS FOR ADDITIONAL INFORMATION. 4 5 6 • FIRE ALARM CONTROL PANEL FURNISHED BY DIVISION 28, INSTALLED BY DIVISION 26. INSTALL SO TOP OF PANEL IS 72" ABOVE FINISHED FLOOR. CIRCUIT AND CONNECT PER RESPECTIVE FIRE ALARM RISER AND PER MANUFACTURER'S RECOMMENDATIONS. COORDINATE FINAL LOCATION WITH OWNER, ENGINEER, AND AHJ DURING CONSTRUCTION. PROVIDE LABEL INDICATING POWER SOURCE, LOCATION AND DISCONNECTING MEANS PER NFPA 72. SEE (28 30 00) FOR ADDITIONAL REQUIREMENTS. • FIRE ALARM REMOTE ANNUNCIATOR PANEL FURNISHED BY DIVISION 28, INSTALLED BY DIVISION 26. INSTALL SO TOP OF PANEL IS 72" ABOVE FINISHED FLOOR. CIRCUIT AND CONNECT PER RESPECTIVE FIRE ALARM RISER AND PER MANUFACTURER'S RECOMMENDATIONS. COORDINATE FINAL LOCATION WITH OWNER, ENGINEER, AND AHJ DURING CONSTRUCTION. • PROVIDE RJ45 DATA JACK ON BACK WALL OF CABINET FOR USE WITH VIDEO EQUIPMENT. COORDINATE EXACT MOUNTING HEIGHT WITH GENERAL CONTRACTOR. 7 8 9 10 11 GENERAL NOTES 1. SEE SHEET GEN/E001 FOR GENERAL NOTES. 2. ALL TAG NAMES TO BE PRECEDED BY "ADM-" UNLESS OTHERWISE DENOTED WITH AN ASTERISK (*). 3. SEE DEVICE TAGNAMES WITHIN THE CABLE AND CONDUIT SCHEDULE FOR ALL CIRCUITING REQUIREMENTS. PROJECT NUMBER CHECKED / APPROVED DATE DRAWING TYPE PREPARED BY /Layout: 22x34DRAWING FACILITY Advanced Engineering and Environmental Services, LLC Water Tower Pl Business Ctr 6901 E Fish Lake Rd Ste 184 Maple Grove, MN 55369 (t) 763-463-5036 (f) 763-463-5037 www.ae2s.comBIM 360://05409-2017-004 Otsego West WWTF Phase 1 Improvements/05409-2017-004_Otsego West_ADM_E_v20.rvt3/25/2022 4:10:51 PMMAR 2022 05409-2017-004 DLH AMW PGM CONST.FIRST FLOOR MAIN BUILDING SYSTEMS PLANOTSEGO, MINNESOTACITY OF OTSEGOOTSEGO WEST WWTF PHASE 1 IMPROVEMENTSADM E104 N O R T H02'4'6'8'10'12" E104 1 FIRST FLOOR MAIN BUILDING SYSTEMS PLAN SYMDATEDESCRIPTIONAPPRI HEREBY CERTIFY THAT THIS PLAN, SPECIFICATION, OR REPORT WASPREPARED BY ME OR UNDER MY DIRECT SUPERVISION AND THAT I AMA DULY LICENSED PROFESSIONAL ENGINEER UNDER THE LAWS OFTHE STATE OF MINNESOTA.SIGNATURE:TYPED NAME: ADAM WAHLERMARCH 28 , 2022 REG. NO. 50599Page 215 CONFORMED B3/1 B3/1 B3/1 B3/1 B3/1 B3/1 B3/1 B3/1 B3/1 B3/1 B3/1 B3/1 G1/3 G1/3 *LPBEI* OH1022 1 SB3 SB3 (EXISTING) PC C LTGC15 4 GENERAL NOTES 1. SEE SHEET GEN/E001 FOR GENERAL NOTES. 2. ALL NON-EMERGENCY LIGHT FIXTURES SHALL BE CIRCUITED TO EXISTING 120/208V PANEL LPBEI UNLESS NOTED OTHERWISE. REUSE 20A/1P BREAKERS TO FEED INTERIOR AND EXTERIOR LIGHTING. 3. ALL TAG NAMES TO BE PRECEDED BY 'UV-' UNLESS OTHERWISE DENOTED WITH AN ASTERISK (*). 4. SEE DEVICE TAGNAMES WITHIN THE CABLE AND CONDUIT SCHEDULE FOR ALL CIRCUITING REQUIREMENTS. 5. SEE EXTERIOR LIGHTING CONTACTOR SCHEMATIC IN 'SD' DRAWINGS FOR ADDITIONAL DETAILS FOR ALL WALL PACKS. CONSTRUCTION NOTES • OVERHEAD DOOR PUSH BUTTON CONTROL STATION FURNISHED WITH THE OVERHEAD DOOR OPERATOR BY DIVISION 8 AND CIRCUITED BY DIVISION 26. • OVERHEAD DOOR OPERATOR BY DIVISION 8 AND CIRCUITED BY DIVISION 26. UTILIZE . PROVIDE NEW XXA/XP BREAKER IN EXISTING PANEL LPBEI. • OVERHEAD DOOR WITH SAFETY BEAM PHOTO EYES FURNISHED WITH OVERHEAD DOOR OPERATOR BY DIVISION 8 AND CIRCUITED BY DIVISION 26. • FURNISH AND INSTALL WALL MOUNTED PHOTOCELL NEAR ROOFLINE, ORIENTATED NORTH, ADJUST FOR AMBIENT LIGHT. SEE EXTERIOR LIGHTING CONTACTOR SCHEMATIC FOR CIRCUITRY. • FURNISH AND INSTALL EXTERIOR LIGHTING CONTROL CONTACTOR. SEE LIGHTING CONTROL SCHEMATIC FOR DETAILS. 1 2 3 4 5 PROJECT NUMBER CHECKED / APPROVED DATE DRAWING TYPE PREPARED BY /Layout: 22x34DRAWING FACILITY Advanced Engineering and Environmental Services, LLC Water Tower Pl Business Ctr 6901 E Fish Lake Rd Ste 184 Maple Grove, MN 55369 (t) 763-463-5036 (f) 763-463-5037 www.ae2s.comBIM 360://05409-2017-004 Otsego West WWTF Phase 1 Improvements/05409-2017-004_Otsego West_UV_E_v20.rvt3/25/2022 2:42:17 PMMAR 2022 05409-2017-004 DLH AMW PGM CONST.MAIN LEVEL LGPM PLANOTSEGO, MINNESOTACITY OF OTSEGOOTSEGO WEST WWTF PHASE 1 IMPROVEMENTSUV E103 N O R T H02'4'6'8'10'12" E103 1 MAIN LEVEL LGPM PLAN SYMDATEDESCRIPTIONAPPRI HEREBY CERTIFY THAT THIS PLAN, SPECIFICATION, OR REPORT WASPREPARED BY ME OR UNDER MY DIRECT SUPERVISION AND THAT I AMA DULY LICENSED PROFESSIONAL ENGINEER UNDER THE LAWS OFTHE STATE OF MINNESOTA.SIGNATURE:TYPED NAME: ADAM WAHLERMARCH 28 , 2022 REG. NO. 50599Page 170 CONFORMED 2 P101 CA 62' - 6"4' - 6"4' - 6" 4' - 6"4' - 6" CA1-AE1 (DO) 1 5' - 0"943.00' FFE 952.00' TOP OF WALL 943.50' 1' - 3"1' - 3" 6 56"FINISHED GRADE 947.00' 2' - 6" 1 ENCASE IN CONCRETE, SEE DETAIL 11/SD/P0025' - 0"1' - 6"PIPE EL 944.33' FINISHED GRADE 947.00' PROJECT NUMBER CHECKED / APPROVED DATE DRAWING TYPE PREPARED BY /Layout: 22x34DRAWING FACILITYI HEREBY CERTIFY THAT THIS PLAN, SPECIFICATION, OR REPORT WAS PREPARED BY ME OR UNDER MY DIRECT SUPERVISION AND THAT I AM A DULY LICENSED PROFESSIONAL ENGINEER UNDER THE LAWS OF THE STATE OF MINNESOTA.SIGNATURE:_________________________________________________TYPED NAME: SCOTT HENRY SCHAEFERMARCH 28, 2022 REG. NO. #48660Advanced Engineering and Environmental Services, LLC Water Tower Pl Business Ctr 6901 E Fish Lake Rd Ste 184 Maple Grove, MN 55369 (t) 763-463-5036 (f) 763-463-5037 www.ae2s.comBIM 360://05409-2017-004 Otsego West WWTF Phase 1 Improvements/05409-2017-004-Otsego_West_CA-P_v20.rvt4/8/2024 2:49:51 PMMAR 2022 05409-2017-004 SJ SHS PWH CONST.CASCADE AERATION STRUCTUREOTSEGO, MNCITY OF OTSEGOOTSEGO WEST WWTF IMPROVEMENTS PHASE 1CA P101 12"0 1'2'3'4'5'6'7' R O N T H P101 1 AERATION STRUCTURE PLAN VIEW P101 2 AERATION STRUCTURE SECTION 12"0 1'2'3'4'5'6'7' INSULATE PIPE, SEE SITE WORK TRENCH DETAILS IMPROVEMENTS 1 24" DI WALL PIPE (MJ X PE), SEE DETAIL 8/SD/P501 5 16" DI WALL PIPE (MJ X PE), SEE DETAIL 8/SD/P501 6 CASCADE AERATION INSERT SYMDATEDESCRIPTIONAPPR104/28/24FIELD ORDER #9INSTRUMENT SCHEDULE TAG # DESCRIPTION TYPE P&ID SPECIFICATIO N FURNISHED BY REMARKS CA1-AE1 PROBE DO CA-IC101 40 91 00 OWNER SEE DETAILS 4/SD/P508 AND 5/SD/P508 EQUIPMENT SCHEDULE TAG # DESCRIPTION TYPE P&ID SPECIFICATIO N REMARKS CA1 CASCADE AERATION INSERT Low Profile CA-IC101 46 51 53 1 1 1 1 1 CONSTRUCTION NOTE SCHEDULE KEYNOTE TYPE KEYNOTE VALUE KEYNOTE DESCRIPTION KEYNOTE SHEET NUMBER CONSTRUCTION 1 REFER TO SW C120 FOR YARD PIPE PROFILE. SW C120 CONSTRUCTION 2 EFFLUENT MANHOLE. SEE CIVIL. SW 120 1 1 2 SHEET RE-ISSUED BY FIELD ORDER 9 June 20, 2025 AE2S 6901 East Fish Lake Rd. Suite 184 Maple Grove, MN 55369-5457 ATTN: Scott Schaefer, PE Re: Otsego West WWTF Improvements Phase 1 RLCG Project No. 2215 Change Order Proposal #: 076 – Additional Grating in PTB Scott, Pricing was requested to furnish and install additional grating near the discharge of the screenings conveyor in the PTB. The total cost to complete this extra work was $14,981.00. Attached is a breakout of the costs. Please let me know if you have any questions. Sincerely, Rice Lake Construction Group Matt Perpich Project Manager 2215 Otsego West WWTF Improvements Phase 1 22360 County Road 12, PO Box 517 6/20/2025 Deerwood, MN 56444 75REV1 HOURS $ RATE TOTAL RATE TOTAL RLCG Labor 32.00 HR 32.00 109.00$ $3,488.00 -$ $0.00 -$ -$ 3,488.00$ RLCG Material 1.00 LS -$ $0.00 200.00$ $200.00 -$ -$ 200.00$ RLCG Equipment 1.00 LS -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Metro 1.00 LS -$ $0.00 8,441.00$ $8,441.00 -$ -$ 8,441.00$ -$ $0.00 $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Misc. Small Tools and Mat'l 5% of Labor 1.00 ea 5.00%174.40$ Sales Tax 1.00 ea 7.375%637.27$ Totals 32.00 3,488.00$ 8,641.00$ -$ -$ 12,940.67$ Rice Lake Mark-up on Subs (5%)-$ Rice Lake Mark-up on Labor, Material, and Equipment (15%)1,819.35$ Bond Cost (1.5%)221.40$ Total Change Order Proposal Request 14,981.00$ Days Requested 0 MATERIAL SUBCONTRACTOR TOTAL EQUIPMENT TOTAL LINE TOTALDESCRIPTIONQTYUNITLABOR RLCG PROJECT #: PROJECT NAME: DATE: COP: CHANGE ORDER PROPOSAL #1693 From:Gary Dewing Date:6/19/2025 Project: Otsego West WWTF Improvements Erection: Erection IS NOT included in base bid. Location:Otsego, MN To:Rice Lake (Michael Benson , Matt Perpich) Inclusions:See Below 055000 - Metal Fabrications Secondary Biological Treatment (SBT) CREDIT:($3,306) Eliminate Aluminum Guardrailing, approx. 17 l.f. ADD:$11,747 Aluminum Guardrailing, approx. 4 l.f. Galvanized Steel Bar Grating approx. 70 sq. ft. (11) Galvanized C6/C8 Framing members approx. 50 l.f. (700#), plus SST epoxy anchors (4) Galvanized L Grating Support approx. 15 l.f. (75#), plus SST epoxy anchors Exclusions:Price (ADD):$8,441 (tax included) Best Regards, Gary Dewing Change Order Proposal METRO MANUFACTURING INC. & METRO ERECTORS INC. (WBE) 465 Kenny Road Saint Paul, MN 55130 PH: 651-776-5455 Fax: 651-776-2095 UP UP UP FLOOR PLAN GENERAL NOTES A. ALL PARTITION TYPES ARE "M8" TYPICALLY UNLESS OTHERWISE NOTED. B. COORDINATE DIMENSIONS W/ ASTERISK (IE - *X'-X") W/ EQUIPMENT VENDOR. C. PROVIDE BULLNOSE ON ALL CMU OUTSIDE CORNERS - TYPICAL. D. ALL DIMENSIONS INDICATED AS 'CLEAR' ARE TO FACE OF FINISH (GYPSUM, TILE, ETC.). E. ALL MASONRY DIMENSIONS ARE TO FACE OF MASONRY UNLESS NOTED OTHERWISE. F. ALL EXTERIOR OPENING DIMENSIONS ARE ROUGH OPENINGS. G. COORDINATE ALL FLOOR OPENING DIMENSIONS AND CLEARANCES FOR DUCTWORK W/ MECHANICAL CONTRACTOR - TYPICAL. H. COORDINATE AND/OR CONFIRM ANY DIMENSIONAL DISCREPENCIES WITH ARCHITECT PRIOR TO INSTALLATION. I. PROVIDE HPC-1 AT WALLS AND CEILING. PROVIDE CSLR-1 AT FLOOR SLAB. 1 1 A401 2 A401 A301 2 A301 1 A3013 STORAGE 101 XC4 XC4 XC4 101 OH10224'-0" 5'-4" 10'-0" 8'-8" 3 A401 4 A401 ______ A501 1 2 7'-4"3'-4"2'-0"A B 07 1 1 A401 2 A401 A301 2 A301 1 A3013 7" / 12"7" / 12" 3 A401 4 A401 EXTENTS OF ICE AND WATER PROTECTION MEMBRANE 14'-0" 01 02 03 6'-10"03 3'-9 1/4" 04 05 05 06 2 A B15'-9"1'-6"1'-6" RA2 1 1 A401 A301 1 A3013 01 02 03 04 05 12'-0" 06 07 08 DEMOLITION GENERAL NOTES A. THE OWNER'S NORMAL OPERATIONS WILL BE CONTINUED DURING DEMOLITION. DEMOLITION CONTRACTOR SHALL NOT INTERFERE WITH THESE OPERATIONS IN ANY WAY WITHOUT THE OWNER'S EXPRESSED CONSENT. B. OWNER WILL OCCUPY PORTIONS OF THE BUILDING IMMEDIATELY ADJACENT TO AREAS OF SELECTIVE DEMOLITION. CONDUCT SELECTIVE DEMOLITION WORK IN MANNER THAT WILL MINIMIZE NEED FOR DISRUPTION OF OWNER'S NORMAL OPERATIONS. REFER TO SPECIFICATIONS FOR MINIMUM ADVANCE NOTICE TO OWNER. C. PROVIDE TEMPORARY BARRICADES AND OTHER FORMS OF PROTECTION TO PROTECT OWNER'S PERSONNEL AND GENERAL PUBLIC FROM INJURY DUE TO SELECTIVE DEMOLITION WORK. D. PROVIDE 1 - HOUR FIRE RESISTANT CONSTRUCTION BARRIERS WHERE REQ'D TO PROTECT EXISTING CONSTRUCTION AND OWNERS OPERATIONS. E. PROTECT FROM DAMAGE EXISTING FINISH WORK THAT IS TO REMAIN IN PLACE AND BECOME EXPOSED DURING DEMOLITION OPERATIONS. F. PROTECT FLOORS WITH SUITABLE COVERING WHEN NECESSARY. G. COVER AND PROTECT FURNITURE, EQUIPMENT, AND FIXTURES FROM SOILAGE OR DAMAGE WHEN DEMOLITION WORK IS PERFORMED IN AREAS WHERE SUCH ITEMS HAVE NOT BEEN REMOVED. H. PRIOR TO CUTTING EXISTING CONSTRUCTION, LOCATE AND IDENTIFY SERVICES TO REMAIN IN OPERATION, INCLUDING ALL FLOOR PENETRATIONS. UNDOCUMENTED CONDITIONS, UTILITY RISERS, ETC. AND ANY WALLS THAT CONTAIN LIFE SAFETY VERTICAL RISERS THAT MUST REMAIN IN OPERATION DURING THE DEMOLITION WORK. I. CONTRACTOR SHALL VERIFY ALL EXISTING BUILDING DIMENSIONS, PARTITION AND WALL LOCATIONS AND FLOOR ELEVATIONS IN FIELD AND NOTIFY THE OWNER'S REPRESENTATIVE OF ANY DISCREPANCIES BEFORE THE START OF WORK. J. WHEN UNANTICIPATED MECHANICAL, ELECTRICAL, OR STRUCTURAL ELEMENTS THAT CONFLICT WITH INTENDED FUNCTION OF DESIGN ARE ENCOUNTERED,INVESTIGATE AND MEASURE BOTH NATURE AND EXTENT OF THE CONFLICT AND NOTIFY OWNER'S REPRESENTATIVE. K. MAINTAIN EXISTING UTILITIES INDICATED TO REMAIN IN SERVICE AND PROTECT THEM AGAINST DAMAGE DURING DEMOLITION OPERATIONS. DO NOT INTERRUPT UTILITIES SERVING OCCUPIED OR USED FACILITIES, EXCEPT WHEN AUTHORIZED IN WRITING BY AUTHORITIES HAVING JURISDICTION. L. WHERE DEMOLITION IS REQ'D BEYOND THE LIMITS OF THE CONTRACT TO ROUTE NEW DUCTWORK, PIPING, CONDUITS ETC., RATED WALLS AND SMOKE BARRIERS SHALL BE PATCHED BY CONTRACTOR REQUIRING PENETRATIONS, ALL FINISHES DAMAGED BY THE WORK SHALL BE RESTORED TO THEIR ORIGINAL CONDITION. M. REPAIR DEMOLITION PERFORMED IN EXCESS OF THAT REQ'D. RETURN ELEMENTS OF CONSTRUCTION AND SURFACES TO REMAIN, TO THE CONDITION EXISTING PRIOR TO START OF OPERATIONS. REPAIR ADJACENT CONSTRUCTION OR SURFACES SOILED OR DAMAGED BY SELECTIVE DEMOLITION. N. PROVIDE SHORING, BRACING AND ANY OTHER MEANS REQ'D TO PROTECT AND MAINTAIN THE SAFETY, INTEGRITY AND STABILITY OF ALL EXISTING AND NEW CONSTRUCTION. O. WHEN ROOFING, GLAZING, FLASHING, COPING OR PORTIONS OF EXTERIOR WALLS ARE REMOVED OR OPENED, SUITABLE WEATHER PROTECTION SHALL BE PROVIDED AND MAINTAINED FOR THE DURATION OF WORK. P. REMOVAL OF ITEMS NOTED INCLUDES REMOVAL OF ANCHORS, ADHESIVES, HARDWARE, CONDUIT, WIRE, PIPING, ETC. FOR A COMPLETE REMOVAL OF THE ITEMS OR SYSTEMS. Q. WHEREVER WATER CLOSETS, FLOOR SINKS OR OTHER EQUIPMENT AND RELATED PIPING ARE TO BE REMOVED, PATCH FLOOR SLAB W/ CONCRETE AS REQUIRED. R. ALL CONCRETE FLOOR SLABS NOTED TO BE REMOVED SHALL BE SAWCUT TO PROVIDE A NEAT JOINT. S. SEE MECHANICAL, CIVIL, AND ELECTRICAL DEMOLITION DRAWINGS FOR ADDITIONAL SCOPE OF DEMOLITION WORK. T. SALVAGE ALL EXISTING REMOVED BRICK FOR PATCHING AND REFINISH WORK AS REQ'D - TYPICAL. U. DEMOLITION OF ANY EXISTING CONSTRUCTION SHALL INCLUDE WHAT IS NECESSARY AND REQ'D TO ACCOMMODATE THE REQUIREMENTS OF NEW CONSTRUCTION. REFER TO THE APPROPRIATE DRAWINGS AS TO THE EXTENT OF NEW CONSTRUCTION TO REMAIN. V. SURFACES SHALL BE CLEANED AND PREPPED WITHIN THE NEW MATERIALS GUIDELINES OF INSTALLATION OF THEIR PRODUCT IN EXISTING CONSTRUCTION. W. ALL DEMOLITION SHALL COMPLY WITH APPLICABLE LOCAL CODES AND STATE CODES AND ORDINANCES. X. REFER TO SPECIFICATIONS FOR ADDITIONAL REQUIREMENTS PROJECT NUMBER CHECKED / APPROVED DATE DRAWING TYPE PREPARED BY /Layout: 22x34DRAWING FACILITYI HEREBY CERTIFY THAT THIS PLAN, SPECIFICATION, OR REPORT WAS PREPARED BY ME OR UNDER MY DIRECT SUPERVISION AND THAT I AM A DULY LICENSED PROFESSIONAL ENGINEER UNDER THE LAWS OF THE STATE OF MINNESOTA.SIGNATURE:___________________________________________________TYPED NAME: ADAM D. BARNETTMARCH 25, 2022 REG. NO. #50657Advanced Engineering and Environmental Services, LLC Water Tower Pl Business Ctr 6901 E Fish Lake Rd Ste 184 Maple Grove, MN 55369 (t) 763-463-5036 (f) 763-463-5037 www.ae2s.com JLG PROJ. NO.: 20164BIM 360://05409-2017-004 Otsego West WWTF Phase 1 Improvements/05409-2017-004_Otsego West WWTF_PTB_A_v20.rvt3/25/2022 11:00:31 AMMAR 2022 20164 ---- JLG CONSTR FLOOR PLANOTSEGO, MNCITY OF OTSEGOOTSEGO WEST WWTF IMPROVEMENTS PHASE 1PTB A201 FLOOR PLAN KEYNOTES KEYNOTE DESCRIPTION 01 DEMOLISH PORTION OF EXISTING RAILING 02 NEW GALVANIZED STEEL FLOOR GRATING. SEE STRUCT. 03 GALVANIZED STEEL PIPE RAILING. SEE DETAIL 11/A007 04 CONTINUOUS RIDGE VENT 05 <SMF-2> GUTTER AND DOWNSPOUT. SEE ELEV. 06 MODIFY EXISTING DOWNSPOUT TO DIRECT WATER TO NEW ROOF. SIZE NEW GUTTER AND DOWNSPOUT TO ACCOMODATE EXISTING ROOF STORMWATER RUNOFF. 07 STOOP; SEE STRUCTURAL. XX NO SCALEA201 2 FIRST FLOOR NO SCALEA201 3 UPPER LEVEL/ ADDITION ROOF 0 4'8'12'16'20'0 4'8'12'16'20'0 4'8'12'16'20' NO SCALEA201 1 FIRST FLOOR PLAN - DEMO DEMOLITION KEYNOTES ID DESCRIPTION 01 DEMOLISH DOOR AND FRAME, PATCH JAMB FOR A SMOOTH FINISH AS REQUIRED. 02 DEMOLISH CANOPY OVER HEAD AND SUPPORTING MEMBERS. PREP WALL FOR NEW CONSTRUCTION AS REQUIRED. 03 DEMOLISH OVERHEAD DOOR AND ALL ASSOCIATED COMPONENTS, INCLUDING BUT NOT LIMITED TO TRACKS, OPERATOR, PHOTO EYES, BLOCKING, ETC. 04 DEMOLISH PORTION OF CIP CONCRETE WALL WHERE INDICATED. CUTS SHALL BE PLUMB AND PROVIDE A SMOOTH FINISH. 05 MODIFY DOWNSPOUT BY TRUNCATING ABOVE NEW BUILDING ADDITION, DIRECT WATER ONTO NEW ROOF TO SPILL INTO NEW DOWNSPOUT. 06 DEMOLISH EXTERIOR WALL FINISH MATERIALS DOWN TO CONCRETE WALL, TYPICAL AT ENTIRE AREA OF NEW CONSTRUCTION TIE-IN. 07 EXISTING ROOF CANOPY AND STRUCTURE TO REMAIN 08 DEMOLISH STRUCTURAL STOOP AND WING WALLS TO DEPTH OF 18" BELOW NEW FINISH FLOOR. XX Page 105 CONFORMED Add Grating July 24, 2025 AE2S 6901 East Fish Lake Rd. Suite 184 Maple Grove, MN 55369-5457 ATTN: Scott Schaefer, PE Re: Otsego West WWTF Improvements Phase 1 RLCG Project No. 2215 Change Order Proposal #: 077 – Add Baffle Walls in SBT Tanks REV1 Scott, Pricing was requested to furnish and install top baffle plates on one wall, and cover up two sets of openings on two lower walls in the SBT Tank. The total cost to perform this work is $30,501.00 Clarifications: - Pricing excludes winter conditions - All work to be completed in (1) SBT train/tank - Draining/Cleaning of SBT Tank not included. Attached is a breakout of the costs. Please let me know if you have any questions. Sincerely, Rice Lake Construction Group Matt Perpich Project Manager 2215 Otsego West WWTF Improvements Phase 1 22360 County Road 12, PO Box 517 7/24/2025 Deerwood, MN 56444 77REV1 HOURS $ RATE TOTAL RATE TOTAL RLCG Labor 72.00 HR 72.00 109.00$ $7,848.00 -$ $0.00 -$ -$ 7,848.00$ RLCG Material - Epoxy Adhesive 1.00 LS -$ $0.00 1,560.00$ $1,560.00 -$ -$ 1,560.00$ RLCG Equipment 1.00 LS -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Vessco - FRP 1.00 LS -$ $0.00 15,300.00$ $15,300.00 -$ -$ 15,300.00$ -$ $0.00 $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Misc. Small Tools and Mat'l 5% of Labor 1.00 ea 5.00%392.40$ Sales Tax 1.00 ea 7.375%1,243.43$ Totals 72.00 7,848.00$ 16,860.00$ -$ -$ 26,343.83$ Rice Lake Mark-up on Subs (5%)-$ Rice Lake Mark-up on Labor, Material, and Equipment (15%)3,706.20$ Bond Cost (1.5%)450.75$ Total Change Order Proposal Request 30,501.00$ Days Requested 0 SUBCONTRACTOR TOTAL EQUIPMENT TOTAL LINE TOTAL CHANGE ORDER PROPOSAL RLCG PROJECT #: PROJECT NAME: DATE: COP: DESCRIPTION QTY UNIT LABOR MATERIAL Enduro is pleased to provide this proposal based upon the following MATERIAL ONLY scope of work: A. SBT TANKS – FRP Miscellaneous Straight Weirs - Materials listed per tank: • FRP flat sheet - 3/8” thick x approx. 12’-0” long x 37” high (5ea) • FRP weir splice plates – 3/8” thick x approx. 12’0” long x 6” wide (cut to length in field from flat sheet) (1ea) • FRP Weir Washers – 1/4" thick x 5”Ø at approx. 12” OC. (approx. 63ea) • FRP L-angle – 3/8” thick x 6” wide x 20’ long (cut to length in field). (3ea) • Full complement of 316SST rod type adhesive anchors and fasteners (Adhesive not by Enduro). 1. Proposal is based on these assumptions: a. FRP thickness as stated U.O.N. b. Premium grade corrosion resistant FRP Isophthalic polyester resin, UV suppressed. c. Enduro Composites is ISO 9001 Certified. d. Material is NSF-61 approved (if required for potable water). e. Weirs and scum baffles per AWWA F102 Standards (if applicable). f. Troughs are per AWWA F101 Standards (if applicable). g. Certified signed and sealed calculations and drawings are not included. If calculations are required, the cost of design review and any adjustment from the design quoted shall be reevaluated by Enduro and repriced accordingly. h. 316 SST fasteners and/or anchors as indicated. (Note: If adhesive type anchors are supplied, the adhesive, adhesive applicators, special tools or equipment and consumables are not included – these are supplied by others). i. Field trimming by the installer may be required (associated equipment, tools, sealant, consumables, etc. not included – supplied by others). j. The proposal is based on the applicability of EPA De Minimis Waiver of Section 436 of P.L. 113-76, Consolidated Appropriations Act of 2014 and/or De Minimis General Applicability Waiver of Section 70914(a) of P.L. 117-58, Build America, Buy America Act, 2021. k. FRP material is manufactured by Pultrusion or Open Mold methods. l. The color shall be Enduro standard dark gray. Proposal No. 25P055 Rev. 2 Date: 7/17/25 To: Rice Lake Construction Project: OTESGO WEST WWTF PHASE 1 Bid Date: NA Location: OTSEGO, MN 55301 Spec Section: EMAIL RECEIVED 7/16/2025 Drawing #: S301 Addenda: NA Rep Firm: Vessco Enduro Sales Rep: Matthew Sumbera m. The manufacturer’s standard one-year material warranty from delivery date applies unless stated otherwise in the clarification/exception section. n. O&M Manuals – if applicable (electronic version only) o. Freight – See Terms for information. p. Submittal/Installation Drawings (11” x 17” sheets). 2. Warranty: a. Warranty for material defects and workmanship shall be for 12 months following date of shipment. 3. Clarifications/Exceptions: a. Clarification: Enduro offers our standard weir and scum baffle, standard wall mount density current baffles, standard launder cover, standard launder trough and supports without signed and sealed calculations and drawings. b. Clarification: Enduro manufactures weirs and scum baffles up to 12 feet long by pultrusion method and panels are CNC machine fabricated with all cut edges and holes factory sealed. c. Clarification: Enduro typically manufactures FRP products with UV stabilizers in standard dark grey color to increase the resistance to UV radiation in lieu of other colors. d. Clarification: Enduro offers rod type anchors (adhesive not included) to meet most current anchor requirements. 4. Proposal does not include: a. Staging, storage, unloading, installation, field labor or testing of any kind. b. Detailing, engineering, or design calcs. This is strictly a materials order only. c. Site visits, or field advisor, unless included in the Scope of Work or Inclusion Section. d. NOTE: Enduro does not include any field visits in this proposal. If a field visit is required Enduro will only verify that the products have generally been installed per our field drawings. Enduro does not certify construction methods. If field visits are required, please add $3000 per trip and $1000 per day after day 1. Enduro requires 4-6 weeks’ notice prior to the required date, anything sooner can be assessed for an expediting fee. e. Grout, gaskets, sealant, adhesive, caulk, etc. unless specified herein. f. Spare parts. g. Pipe flanged bolt and gasket sets. h. O&M Manuals if applicable (hardcopies). i. Taxes, permits, duties, brokerage fees, or bonds. j. Any material to modify concrete or other adjoining material surfaces. k. Miscellaneous stainless-steel hardware unless otherwise noted in scope above. l. Compliance with Specifications, Drawings, or Addenda not listed in this proposal. 5. Terms: a. FOB Factory (Houston, TX). Pricing excludes freight to jobsite – see Section 7 for more details. b. Pricing is valid for purchase orders or Letter of Intent received and accepted within 30 days from the date of the proposal, for goods to be released to manufacture within 180 days from the date of the proposal, provided release for shipment is authorized upon completion of the goods. Pricing may be revised on orders/LOI received more than 90 days after proposal. Orders not released for manufacture within 180 days of the date of the proposal or released for manufacture but not released for immediate delivery upon completion of the goods, are subject to Enduro’s Price Escalation Index. A copy of the index provisions is available upon request. c. Payment terms (net 30 days and subject to credit approval): Minimum 50% due execution of contract, additional 50% upon shipment of material. d. Proposal per Enduro Composites’ standard terms & conditions. 6. Estimated Lead Time for Shipping: a. 9-11 weeks after written approval of parts list for Weirs. b. 10-16 weeks after written approval for submittal package for sprayed up parts. - More detailed lead time will be provided after approval of submittal package. -Delays in approvals may cause longer lead times. *Lead times may vary based on raw material availability and will be determined after approved submittal and release to manufacture. 7. Price (USD): Contact Vessco for pricing. Estimated FREIGHT COST IS NOT included in total or unit prices. The actual charge shall be based on weight and freight cost at time of shipment. We look forward to working with you and hope this proposal meets with your satisfaction. Matthew Sumbera, National Sales Manager – Water & Wastewater Products Email: msumbera@endurocomposites.com $15,300.00 Freight cost of $3,300.00 IS TERMS AND CONDITIONS OF SALE 1. DEFINITIONS In these Standard Terms of Sale (“Terms”), the following words shall have the following meanings (unless the context otherwise requires): “Company” means Enduro Composites Inc., a Delaware corporation; “Contract” means any purchase order, sales agreement, or other agreement for the sale of Goods between Company and Customer to which these Terms apply; “Customer” means the person, firm or company who has placed an order for Goods from Company; “Delivery Point” means Company’s address or such other address as Company may specify to Customer; and “Goods” means all goods and/or services to be supplied under the Contract to Customer by Company. The following words are defined in the sections below: “Delivery” (Section 5.1); “HS ABC Policy” (Section 13.2); “HS Code of Conduct” (Section 13.2); “Orders” (Section 2.1); “Warranty” (Section 7.1); and “Warranty Period” (Section 7.3). 2. GENERAL 2.1 Any quotation is not an offer to sell Goods. All orders by Customer for the Goods (“Orders”), if accepted by Company in its sole discretion, will be accepted subject only to these Terms. DIFFERENT OR ADDITIONAL TERMS PROPOSED BY CUSTOMER ON OR IN CONNECTION WITH CUSTOMER’S PURCHASE ORDER FORMS OR OTHER DOCUMENTATION SHALL NOT APPLY TO THE PURCHASE OF GOODS HEREUNDER AND ARE HEREBY EXPRESSLY REJECTED AND SHALL NOT BECOME PART OF THE CONTRACT. COMPANY’S AGREEMENT TO SELL GOODS TO CUSTOMER IS EXPRESSLY LIMITED TO THESE TERMS AND, IF APPLICABLE, A WRITTEN AND SIGNED AGREEMENT BETWEEN CUSTOMER AND COMPANY TO WHICH THESE TERMS ARE ATTACHED. 2.2 Company reserves the right at any time prior to Delivery, to increase the price of the Goods to reflect any increase in the cost to Company which is due to any factor beyond the control of Company (including but not limited to, any foreign exchange fluctuation, currency regulation, alteration of duties, significant increase in the costs of labor, materials or any other costs of manufacture), any change in Delivery dates, quantities or specifications for the Goods which is requested by Customer, or any delay caused by any instructions of Customer or failure of Customer to give Company adequate information or instructions. 2.3 If, subsequent to this Contract, any sale is concluded with the same Customer by fax, telegram, electronically or orally, or by any combination of these, without express reference to these Terms, these Terms shall apply unless expressly modified in writing signed by both Company and Customer. 2.4 Any statement or representation by the Company or its employees or agents upon which the Customer intends to rely must be set out in writing and signed by both parties. Any statement or representation which is not so confirmed in writing is followed or acted upon entirely at the Customer’s own risk. For the avoidance of doubt, illustrations, weights, measures, performance capabilities, application suitability information and other data set out in the sales literature of Company are statements of opinion and are provided for information only and form no part of the Contract. 2.5 All quotations shall automatically expire on the expiration date listed in the quotation, if any, but in no event later than thirty (30) days from issuance and are subject to withdrawal by written or oral notice to Customer at any time. 2.6 Verbal, telephone, fax, or email Orders will be executed at Customer’s sole risk and must be confirmed in writing received by Company within 72 hours. No Order shall be deemed to have been accepted by Company until written acknowledgement of its acceptance is received by Customer from Company. 2.7 No Order which has been accepted by Company may be cancelled by Customer except with the agreement in writing of Company, and Customer shall indemnify Company in full against all loss (including loss of profit), costs (including the cost of all labor and materials used), damages, charges and expenses incurred by Company as a result of cancellation. 2.8 Company may cancel an Order at any time by serving notice in writing on Customer if it does not receive, on request, satisfac tory (in Company’s sole opinion) credit references in relation to Customer. If Company cancels an Order pursuant to this Section it shall have no liability whatsoever for any liabilities, losses, damages, costs or expenses whatsoever incurred, suffered or paid by Customer as a result of or in connection with such cancellation. 3. PRICES 3.1 In the supply of Goods, prices do not include the cost of Delivery or of any import or customs duties or any other applicable taxes or governmental impositions unless otherwise stated in writing by Company, which taxes, impositions and duties shall be the sole responsibility of Customer. All prices are subject to the addition of any applicable sales tax. 3.2 Company reserves the right at any time prior to Delivery, to increase the price of the Goods to reflect any increase in the cost to Company which is due to any factor beyond the control of Company (including but not limited to, any foreign exchange fluctuation, currency regulation, alteration of duties, significant increase in the costs of labor, materials or any other costs of manufacture), any change in Delivery dates, quantities or specifications for the Goods which is requested by Customer, or any delay caused by a ny instructions of Customer or failure of Customer to give Company adequate information or instructions. 4. PAYMENT 4.1 Subject to Section 4.2 below, payment of the price for the Goods is due in U.S. Dollars in cash, wire or ACH funds no later than thirty (30) days following Delivery of the Goods, unless otherwise agreed in writing. 4.2 If the Customer wrongfully fails to take Delivery of the Goods, Company shall be entitled to invoice Customer for the price at any time after Company has tendered Delivery. 4.3 No payment shall be deemed to have been received by the Company until Company has received cleared funds. 4.4 In the event of default in payment by Customer, Company shall be entitled (without prejudice to any other right or remedy it may have under these Terms or otherwise) to charge interest on a daily basis (after as well as before judgment) on any amount outstanding at the annual rate of four percent (4%) above the prime rate published by JPMorgan Chase Bank from time to time. 4.5 In the event of any dispute, Customer shall not be entitled to withhold payment of the price of the Goods or any agreed payments or to any right of set-off, deduction, counterclaim, abatement or otherwise against any payment due to Company under any Contract. 4.6 In respect of Goods sold for export, unless otherwise agreed in writing, payment shall be made (a) by irrevocable letter of c redit confirmed with a clearing bank approved by Company or (b) prior to manufacture / fabrication 4.7 Time for payment shall be of the essence of the Contract. 4.8 All payments payable to Company under the Contract shall become due immediately on its termination. 5. DELIVERY 5.1 Unless otherwise agreed in writing by Company, delivery shall be deemed to take place when the Goods are made available by Company at the Delivery Point for collection by Customer or its carrier (“Delivery”). 5.2 Any and all dates and periods specified by Company for Delivery are estimates only and do not constitute fixed times for Delivery. Delivery shall not be of the essence of the Contract and shall not be made of the essence by notice. Company shall have no liability for any damages, losses, costs or expenses whatsoever or in connection with the failure by Company to meet any Delivery times specified in the Order. Customer shall have no right to cancel an Order for a failure of Company to meet any Delivery times. 5.3 Company will endeavor to comply with any reasonable request by Customer for postponement of Delivery but shall be under no obligation to do so and Customer is obliged to take Delivery at such date and time as specified by Company. Where postponement is agreed by Company in writing Customer shall, if required, pay all costs and expenses including a reasonable charge for storage occasioned thereby and any costs incurred by Company in relation to any insurance payments reasonably made by it. Company reserves the right to deliver the Goods to Customer in instalments. Where the Goods are delivered in instalments, each Delivery shall constitute a separate contract and failure by Company to deliver any one or more of the instalments in accordance with these Terms or any claim by Customer in respect of any one or more instalments shall not entitle Customer to treat the Contract as a whole as repudiated. 5.4 The date for Delivery shall in every case be dependent upon prompt receipt of all necessary information, final instructions, or approvals from the Customer. 5.5 If Customer is ordering Goods for Delivery outside of the country of manufacture by Company, such Goods may be subject to import duties and taxes which are levied when the Goods reach the specified destination. Customer will be responsible for payment of such import duties and taxes. Customer will comply with all laws and regulations of the country for which the Goods are destined, and Company will not be liable for any breach of those laws. 5.6 The Customer shall (and shall procure that its sub-contractors and agents shall): (a) observe the work rules and safety regulations of Company while on Company’s premises; and (b) strictly follow all instructions and installation materials related to the Goods and not make any alteration, modification or addition to the Goods or packaging (and any alteration of the Goods, or use of non-approved parts, products or packaging with the Goods, shall be a material breach of these Terms and voids any warranties made by Company for the Goods). 6. RISK AND TITLE 6.1 Title to the Goods will pass to Customer upon Company’s Delivery of the Goods. 6.2 Unless otherwise agreed between Company and Customer in writing, risk of damage to or loss of the Goods shall pass to Customer upon Delivery. When Goods are transported by Company’s own vehicles, Delivery shall be deemed to take place at the moment the Goods are lifted from Company’s vehicle. 6.3 No claim for Goods damaged in transit will be considered by Company unless Company used its own transport for Delivery and unless: (a) an appropriately qualified signature, e.g. “Goods received damaged, (signed)” is clearly made by Customer on the delivery note; (b) Company is advised in writing per motor carrier rules; (c) Company is advised in writing within three days of Delivery. 6.4 No allowance for claims for short deliveries will be made unless (a) notice is provided to the Company within three days of Delivery and (b) the Company is given an opportunity to verify the same. Where goods are to be stored on Customer’s site prior to use, bundled goods and crated goods should not be opened but inventoried for short deliveries as a sealed bundle or crate. Once opened, n otice and opportunity to verify any shortages must be given as provided above. 6.5 For the avoidance of doubt, where Customer collects the Goods from the Delivery Point or where a third party collects the Goods for transport to Customer, Company shall have no liability to Customer for any Goods damaged in transit. 7. WARRANTY AND LIABILITY 7.1 For and during the Warranty Period (as defined below), the Company warrants that the Goods will comply in all material respects with any specifications for the Goods agreed to in writing between Company and Customer. If no specification for the Goods has been agreed to in writing between Company and Customer, Company warrants for and during the Warranty Period that the Goods will comply in all material respects with the specifications published by Company in relation to the Goods from time to time (if any), or, in the absence of any specification (agreed or published), the Goods will be free from material defects in workmanship or materials (the “Warranty”). 7.2 THE FOREGOING WARRANTY IS IN LIEU OF AND EXCLUDES ALL OTHER WARRANTIES NOT EXPRESSLY SET FORTH HEREIN, WHETHER EXPRESS OR IMPLIED BY OPERATION OF LAW OR OTHERWISE, INCLUDING BUT NOT LIMITED TO ANY IMPLIED WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. 7.3 Any claim for defect with respect to the Goods sold hereunder shall be deemed waived by Customer unless Company is notified i n writing, in the case of defects apparent on visual inspection, within sixty (60) days from Delivery, or, in the case of defects not apparent on visual inspection, within twelve (12) months from Delivery (such 60 days or 12 months, as applicable, the “Warranty Period”). All Goods claimed to be defective shall be held subject to Company’s inspection, and Company shall not be liable for the cost of any repairs performed without its express written consent. The Goods claimed to be defective may be returned prepaid to Company’s plant for inspection in accordance with return shipping instructions that Company shall furnish to Customer upon receipt of Customer’s notice of claim. If the claim is established, the Company will reimburse the Customer for all shipping costs incurred in connection with such return. 7.4 This Warranty is made to Customer and does not extend to any other person or entity and is not assignable. 7.5 This Warranty shall not apply (a) if the Goods have been subject to improper storage, accident, misuse or unauthorized modifications, alterations, or repairs, or have not been installed, operated, and maintained in accordance with procedures approved by Company, (b) to normal wear and tear, (c) to any errors, omissions or defects contained in the specifications or designs provided by Customer or (d) to any components manufactured by Customer or a third party not approved by Company. 7.6 Customer shall indemnify and keep Company indemnified in full against all and any direct, indirect or consequential liabilities (all three of which terms include without limitation loss of profit, loss of business, depletion of goodwill and like loss), losses, claims, damages, costs and expenses (including all legal and other professional expenses) awarded against or incurred or paid by Company as a result of or in connection with any breach of the Contract by Customer and death or personal injury to Company’s employees or agents while such employees or agents are on any premises of Customer in connection with the Contract. Without limiting the foregoing, Customer shall indemnify Company against all claims by any third parties for any claims, loss, damage or expense resulting from the breach by Customer of any of its obligations under these Terms, including without limitation, any modification, misuse, or unapproved alteration of, or use of non-approved components with, the Goods. 7.7 To the fullest extent permitted by law, under no circumstances will Company be liable to Customer for an amount in excess of the price paid, or to be paid, for the Goods for any claims, losses, liens, costs, liabilities, causes of action, suits, demands, judgments, obligations, fines, penalties, damages, requirements, violations, and expenses (including without limitation, attorneys’ fees, court costs, and costs of investigation) of any nature, kind, or description, whether based in contract, warranty, indemnity, or tort (including negligence and strict liability), of any person or entity, directly or indirectly, arising out of, resulting from or related to the Contract or the Goods. 8. TERMINATION 8.1 Company shall be entitled, without prejudice to Company’s other rights and remedies, either to terminate wholly or in part any or every Contract between Company and Customer and/or to suspend any further deliveries of Goods in any of the following circumstances: (a) non-compliance by Customer with Company’s terms of payment; (b) If the Customer has failed to provide a letter of credit or guarantee, bill of exchange or any other security required by the Contract or reasonably requested by Company. (c) upon Customer’s dissolution, insolvency, filing of a voluntary or involuntary petition under any law relating to bankruptcy, appointment by a court of a temporary or permanent receiver, trustee or custodian for Customer’s business, or an assignment for the benefit of creditors, of Customer; (d) Customer becomes unable to satisfy its debts as they fall due or ceases or threatens to cease to carry on business; (e) Customer or any connected person commits any breach of this or any other Contract whenever made between Customer and Company; or (f) there has been, or Company suspects that there has been, a breach or there has been a breach of any of the provisions of Section 13 below. 9. CONFIDENTIALITY AND INTELLECTUAL PROPERTY RIGHTS 9.1 All intellectual property, including without limitation, all drawings, installation instructions, documents, confidential records, computer software and other information supplied by Company or otherwise obtained by Customer, whether produced by itself or a third party, are supplied on the express understanding that all intellectual property rights are reserved to Company (or the third party) and that Customer will not, without the written consent of Company, give away, loan, exhibit or sell any such intellectual property or other information or extracts from them, or copies of them, or use them in any way except in connection with the Goods in respect of which they are issued. 9.2 All claims for alleged infringement of patents, trademarks, registered designs, design rights or copyright received by Customer relating to the Goods must be notified immediately to Company. If requested by Company, Company shall be entitled to have conduct of any proceedings relating to any such claim in such manner as Company thinks fit and Customer will provide Company such reasonable assistance as Company may request. The cost of any such proceedings will be borne by Company. 9.3 If any allegations shall be made against Customer to the effect that the supply of the Goods infringes the intellectual property rights of any third party or Company has reason to believe that such allegation is likely to be made, Company may at its option and expense modify or replace the Goods so as to avoid the infringement (but without adversely affecting the overall performance of the Goods), or obtain for the benefit of Customer the right to continue to use the Goods, or repurchase the Goods at the Contract Price as reduced by a reasonable provision for depreciation. If Company pursues any of such options, Customer will have no rights or remedies aga inst Company arising directly or indirectly out of the alleged infringement. 10. FORCE MAJEURE In the event of the performance of any obligation by the Company being prevented, delayed or in any way interfered with by war, riot, civil commotion, strikes, lock-outs, accidents, flood, fire, explosion, or by any other cause beyond its reasonable control (including the delay or failure to supply of any suppliers of the Company) the Company may suspend or treat as impossible the performance of any obligation to Customer without liability for any loss. 11. HEALTH AND SAFETY Customer agrees to pay due regard to any information supplied by Company relating to the use for which the Goods are designed or have been tested or concerning conditions necessary to ensure that they will be safe and without risk to health at all times when they are being set, used, cleaned, serviced or maintained by any person and Customer undertakes to take such steps as may be specified by such information or otherwise necessary to ensure that as far as is reasonably practicable the Goods will be safe and without risk to health at all times as mentioned above 12. TESTING AND INSPECTION 12.1 Testing and inspection if specified by Customer or his agent shall be at Company’s desired location (at Customer’s expense) and such testing and inspection shall be final and conclusive as to the results thereof. 12.2 Company shall not be obliged to produce test and performance certificates or safety critical certificates unless requested by Customer and accepted by Company in writing. 12.3 In addition to any costs incurred by the Company in testing the Goods, Customer shall pay for all test pieces which comply with specification. 13. COMPLIANCE 13.1 Customer shall comply with all relevant laws, including any applicable anti-corruption laws in connection with the Contract and Company’s business and shall immediately notify Company if it discovers or suspects that any of its officers, directors, employees or representatives are acting or have acted in a way which violates such laws. 13.2 Customer acknowledges that Company has a code of responsible business: The Hill & Smith PLC Code of Business Conduct (“HS Code of Conduct”). The HS Code of Conduct, together with Company’s Anti-Bribery and Corruption Policy (“HS ABC Policy”), are available at www.hsgroup.com and Customer shall, at all times, conduct, and cause its officers, directors, employees and/or representatives conduct, business ethically and in accordance with the relevant provisions of the HS Code of Conduct and the HS ABC Policy, as each may be updated from time to time. This clause shall apply whether or not Customer is acting pursuant to the Contract or its relationship with Company. 13.3 Customer agrees that it must be able to demonstrate its compliance with the requirements referred to in this Section 13 at the request of and to the satisfaction of Company, which includes, but is not limited to, Company having the right to inspect any site involved in work for Company and requiring Customer to sign an annual certificate certifying compliance. If Customer fails to comply with this Section 13, Company shall be entitled, in its sole discretion, to terminate the Contract and any other agreement between Customer and Company without penalty to Company, but with obligations for Customer to remedy any damages suffered by Company as a result of such termination or as a result of the breach of contract. 14. TOOLING 14.1 All tools, dies, and molds are integral parts of the Company’s manufacturing process and all charges paid for same by Customer will be considered as part of the purchase price of Goods ordered. Customer shall acquire no title in such tools, dies, and molds and shall have no right to remove the same from Company’s possession. 15. GOODS RETURNED 15.1 Goods may not be returned without the Company’s prior written permission unless otherwise agreed upon. Stock items, when returned, will be credited at the lowest prevailing price, and subject to a minimum charge of twenty-five percent (25%) for handling and restocking. Return transportation charges must be prepaid. Special order or non-standard are not subject to cancellation, change, reduction in amount, nor return for credit without written consent and upon terms which indemnify us fully against loss. Only merchandise in resalable condition will be accepted. 16. MISCELLANEOUS 16.1 In the case of any Order for the export of Goods, the Schedule to the Uniform Law on International Sales Act 1967 shall not in any circumstances apply to the Contract and neither shall the limits imposed by the Unfair Contract Terms Act 1977 on the extent to which liability can be excluded or limited. The United Nations Convention on Contracts for the International Sale of Goods shall have no application to the purchase of Goods, these Terms or actions hereunder or contemplated hereby. 16.2 Any failure to exercise or any delay by Company in exercising a right or remedy provided by this Contract or at law or in equity will not constitute a waiver of the right or remedy or a waiver of any other rights or remedies. A waiver of a breach of any of the terms of the Contract or of a default under these Terms will not constitute a waiver of any other breach or default and will not affect the other terms of the Contract. 16.3 The customer shall not, without the written consent of Company, assign (including by operation of law), transfer, mortgage, or grant a lien on any of its rights under any Contract or purport to do the same. 16.4 Company shall be entitled to appoint one or more sub-contractors to carry out all or any of its obligations under any Contract and shall for the avoidance of doubt be entitled to assign any interest or rights that it has in relation to any Contract. 16.5 If any provision of these Terms shall be held invalid or unenforceable in whole or in part then the unaffected provisions shall remain in full force and effect. Headings appear for convenience only and shall not affect the construction of these Terms. 16.6 The Contract and any non-contractual obligations arising out of or in connection with it shall be governed and interpreted exclusively according to the laws of the State of Texas. The parties hereby agree to submit to the exclusive jurisdiction of the courts in the State of Texas provided that the Company may at its option file suit in the state in which Customer is organized or located, including action to obtain any remedy (including injunctive relief). 16.7 There are no third party beneficiaries to these Terms July 9, 2025 AE2S 6901 East Fish Lake Rd. Suite 184 Maple Grove, MN 55369-5457 ATTN: Scott Schaefer, PE Re: Otsego West WWTF Improvements Phase 1 RLCG Project No. 2215 Change Order Proposal #: 078 – Misc. Changes Group A-Process Piping and Channels Scott, Throughout the course of the project, Rice Lake completed additional miscellaneous process piping and channel work. The total cost to complete this extra work was $23,457.00. Attached is a breakout of the costs. Please let me know if you have any questions. Sincerely, Rice Lake Construction Group Matt Perpich Project Manager 2215 Otsego West WWTF Improvements Phase 1 22360 County Road 12, PO Box 517 7/9/2025 Deerwood, MN 56444 78 HOURS $ RATE TOTAL RATE TOTAL CA Influent Pipe Adjustments RLCG Labor 17.00 HR 17.00 106.00$ $1,802.00 -$ $0.00 -$ -$ 1,802.00$ RLCG Material 1.00 LS -$ $0.00 2,793.00$ $2,793.00 -$ -$ 2,793.00$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Blower Piping Changes in STB -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 12.00 HR 12.00 106.00$ $1,272.00 -$ $0.00 -$ -$ 1,272.00$ RLCG Material 1.00 LS -$ $0.00 1,556.12$ $1,556.12 -$ -$ 1,556.12$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Removing Risers in WAS Storage Tank & Rotating 90's -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 9.00 HR 9.00 106.00$ $954.00 -$ $0.00 -$ -$ 954.00$ RLCG Material LS -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Adding Chemical Feed Drains -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 2.00 HR 2.00 106.00$ $212.00 -$ $0.00 -$ -$ 212.00$ RLCG Material 1.00 LS -$ $0.00 422.98$ $422.98 -$ -$ 422.98$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ MTB Air Dryer Bypass -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 4.00 HR 4.00 106.00$ $424.00 -$ $0.00 -$ -$ 424.00$ RLCG Material 1.00 LS -$ $0.00 150.00$ $150.00 -$ -$ 150.00$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Adding (2) 45's on FSB Rescreen Line -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 12.00 HR 12.00 106.00$ $1,272.00 -$ $0.00 -$ -$ 1,272.00$ RLCG Material 1.00 LS -$ $0.00 1,383.38$ $1,383.38 -$ -$ 1,383.38$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Adding (2) Megalugs in FSB to Support Grating -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 3.00 HR 3.00 106.00$ $318.00 -$ $0.00 -$ -$ 318.00$ RLCG Material 1.00 LS -$ $0.00 536.46$ $536.46 -$ -$ 536.46$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Caulking Stop Plates at FSB Channel -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 3.00 HR 3.00 106.00$ $318.00 -$ $0.00 -$ -$ 318.00$ RLCG Material 1.00 LS -$ $0.00 50.00$ $50.00 -$ -$ 50.00$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Adding Tee's and Valves to the Mixed Gas Control Modules $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 4.00 HR 4.00 106.00$ $424.00 -$ $0.00 -$ -$ 424.00$ RLCG Material 1.00 LS -$ $0.00 178.74$ $178.74 -$ -$ 178.74$ MATERIAL SUBCONTRACTOR TOTAL EQUIPMENT TOTAL LINE TOTALDESCRIPTIONQTYUNITLABOR RLCG PROJECT #: PROJECT NAME: DATE: COP: CHANGE ORDER PROPOSAL 2215 Otsego West WWTF Improvements Phase 1 22360 County Road 12, PO Box 517 7/9/2025 Deerwood, MN 56444 78 RLCG PROJECT #: PROJECT NAME: DATE: COP: CHANGE ORDER PROPOSAL RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Cutting notches into Slide Gate $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 4.00 HR 4.00 106.00$ $424.00 -$ $0.00 -$ -$ 424.00$ RLCG Material LS -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ STB Water Piping $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 8.00 HR 8.00 106.00$ $848.00 -$ $0.00 -$ -$ 848.00$ RLCG Material 1.00 LS -$ $0.00 350.00$ $350.00 -$ -$ 350.00$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Lowering PTB Screen $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 9.00 HR 9.00 106.00$ $954.00 -$ $0.00 -$ -$ 954.00$ RLCG Material 1.00 LS -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Adding Oil Draings to Equipment (No oil costs included)-$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 12.00 HR 12.00 106.00$ $1,272.00 -$ $0.00 -$ -$ 1,272.00$ RLCG Material 1.00 LS -$ $0.00 400.00$ $400.00 -$ -$ 400.00$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ PTB Reuse Water Piping -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 6.00 HR 6.00 106.00$ $636.00 -$ $0.00 -$ -$ 636.00$ RLCG Material 1.00 LS -$ $0.00 150.00$ $150.00 -$ -$ 150.00$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Misc. Small Tools and Mat'l 5% of Labor 1.00 ea 5.00%556.50$ Sales Tax 1.00 ea 7.375%587.84$ Totals 105.00 11,130.00$ 7,970.68$ -$ -$ 20,245.02$ Rice Lake Mark-up on Subs (5%)-$ Rice Lake Mark-up on Labor, Material, and Equipment (15%)2,865.10$ Bond Cost (1.5%)346.65$ Total Change Order Proposal Request 23,457.00$ Days Requested 0 July 9, 2025 AE2S 6901 East Fish Lake Rd. Suite 184 Maple Grove, MN 55369-5457 ATTN: Scott Schaefer, PE Re: Otsego West WWTF Improvements Phase 1 RLCG Project No. 2215 Change Order Proposal #: 079 – Misc. Changes Group B-Earthwork and Sitework Scott, Throughout the course of the project, Rice Lake completed additional miscellaneous earthwork and sitework. The total cost to complete this extra work was $13,723.00. Attached is a breakout of the costs. Please let me know if you have any questions. Sincerely, Rice Lake Construction Group Matt Perpich Project Manager 2215 Otsego West WWTF Improvements Phase 1 22360 County Road 12, PO Box 517 7/9/2025 Deerwood, MN 56444 79 HOURS $ RATE TOTAL RATE TOTAL -$ $0.00 -$ $0.00 -$ -$ -$ Additional Black Dirt Requested by City -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 21.00 HR 21.00 106.00$ $2,226.00 -$ $0.00 -$ -$ 2,226.00$ RLCG Material 1.00 LS -$ $0.00 3,555.77$ $3,555.77 -$ -$ 3,555.77$ RLCG Equipment 13.00 HR -$ $0.00 -$ $0.00 -$ 2,275.00$ 2,275.00$ RLCG Sub 1.00 LS -$ $0.00 -$ $0.00 1,767.11$ -$ 1,767.11$ Additional Erosion Control Blankets -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor HR 0.00 106.00$ $0.00 -$ $0.00 -$ -$ -$ RLCG Material LS -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Equipment HR -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Sub 1.00 LS -$ $0.00 -$ $0.00 1,929.00$ -$ 1,929.00$ -$ $0.00 -$ $0.00 -$ -$ -$ Misc. Small Tools and Mat'l 5% of Labor 1.00 ea 5.00%111.30$ Sales Tax 1.00 ea 7.375%262.24$ Totals 21.00 2,226.00$ 3,555.77$ 3,696.11$ 2,275.00$ 12,126.42$ Rice Lake Mark-up on Subs (5%)184.81$ Rice Lake Mark-up on Labor, Material, and Equipment (15%)1,208.52$ Bond Cost (1.5%)202.80$ Total Change Order Proposal Request 13,723.00$ Days Requested 0 MATERIAL SUBCONTRACTOR TOTAL EQUIPMENT TOTAL LINE TOTALDESCRIPTIONQTYUNITLABOR RLCG PROJECT #: PROJECT NAME: DATE: COP: CHANGE ORDER PROPOSAL July 9, 2025 AE2S 6901 East Fish Lake Rd. Suite 184 Maple Grove, MN 55369-5457 ATTN: Scott Schaefer, PE Re: Otsego West WWTF Improvements Phase 1 RLCG Project No. 2215 Change Order Proposal #: 080 – Misc. Changes Group C-Instrumentation Scott, Throughout the course of the project, Rice Lake completed additional work on instrumentation. The total cost to complete this extra work was $3,009.00. Attached is a breakout of the costs. Please let me know if you have any questions. Sincerely, Rice Lake Construction Group Matt Perpich Project Manager 2215 Otsego West WWTF Improvements Phase 1 22360 County Road 12, PO Box 517 7/9/2025 Deerwood, MN 56444 80 HOURS $ RATE TOTAL RATE TOTAL Moving Instruments on Air Drops in SBT (Costs to-date)-$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 10.00 HR 10.00 106.00$ $1,060.00 -$ $0.00 -$ -$ 1,060.00$ RLCG Material 1.00 LS -$ $0.00 100.00$ $100.00 -$ -$ 100.00$ RLCG Equipment 1.00 LS -$ $0.00 -$ $0.00 -$ 250.00$ 250.00$ -$ $0.00 -$ $0.00 -$ -$ -$ Stilling Wells for MTB -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 4.00 HR 4.00 106.00$ $424.00 -$ $0.00 -$ -$ 424.00$ RLCG Material 1.00 LS -$ $0.00 424.84$ $424.84 -$ -$ 424.84$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Rotated Effluent Flow Meter $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 2.00 HR 2.00 106.00$ $212.00 -$ $0.00 -$ -$ 212.00$ RLCG Material 1.00 LS -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Misc. Small Tools and Mat'l 5% of Labor 1.00 ea 5.00%84.80$ Sales Tax 1.00 ea 7.375%38.71$ Totals 16.00 1,696.00$ 524.84$ -$ 250.00$ 2,594.35$ Rice Lake Mark-up on Subs (5%)-$ Rice Lake Mark-up on Labor, Material, and Equipment (15%)370.63$ Bond Cost (1.5%)44.47$ Total Change Order Proposal Request 3,009.00$ Days Requested 0 MATERIAL SUBCONTRACTOR TOTAL EQUIPMENT TOTAL LINE TOTALDESCRIPTIONQTYUNITLABOR RLCG PROJECT #: PROJECT NAME: DATE: COP: CHANGE ORDER PROPOSAL July 9, 2025 AE2S 6901 East Fish Lake Rd. Suite 184 Maple Grove, MN 55369-5457 ATTN: Scott Schaefer, PE Re: Otsego West WWTF Improvements Phase 1 RLCG Project No. 2215 Change Order Proposal #: 081 – Misc. Changes Group D-Buildings/Structural Scott, Throughout the course of the project, Rice Lake completed various additional building and structural work. The total cost to complete this extra work was $3,203.00. Attached is a breakout of the costs. Please let me know if you have any questions. Sincerely, Rice Lake Construction Group Matt Perpich Project Manager 2215 Otsego West WWTF Improvements Phase 1 22360 County Road 12, PO Box 517 7/9/2025 Deerwood, MN 56444 81 HOURS $ RATE TOTAL RATE TOTAL Modify PTB Roof -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 4.00 HR 4.00 106.00$ $424.00 -$ $0.00 -$ -$ 424.00$ RLCG Material 1.00 LS -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Raising CA Stair Foundation Wall Elevation Change -$ $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 6.00 HR 6.00 106.00$ $636.00 -$ $0.00 -$ -$ 636.00$ RLCG Material 1.00 LS -$ $0.00 150.00$ $150.00 -$ -$ 150.00$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ PTB Conveyor Drain $0.00 -$ $0.00 -$ -$ -$ RLCG Labor 10.00 HR 10.00 106.00$ $1,060.00 -$ $0.00 -$ -$ 1,060.00$ RLCG Material 1.00 LS -$ $0.00 350.00$ $350.00 -$ -$ 350.00$ RLCG Equipment -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ -$ $0.00 -$ $0.00 -$ -$ -$ Misc. Small Tools and Mat'l 5% of Labor 1.00 ea 5.00%106.00$ Sales Tax 1.00 ea 7.375%36.88$ Totals 20.00 2,120.00$ 500.00$ -$ -$ 2,762.88$ Rice Lake Mark-up on Subs (5%)-$ Rice Lake Mark-up on Labor, Material, and Equipment (15%)393.00$ Bond Cost (1.5%)47.34$ Total Change Order Proposal Request 3,203.00$ Days Requested 0 RLCG PROJECT #: PROJECT NAME: DATE: COP: CHANGE ORDER PROPOSAL MATERIAL SUBCONTRACTOR TOTAL EQUIPMENT TOTAL LINE TOTALDESCRIPTIONQTYUNITLABOR July 16, 2025 AE2S 6901 East Fish Lake Rd. Suite 184 Maple Grove, MN 55369-5457 ATTN: Scott Schaefer, PE Re: Otsego West WWTF Improvements Phase 1 RLCG Project No. 2215 Change Order Proposal #: 082 – Natural Gas Use Credit Scott, It was approved in the Fall of 2023 for Rice Lake to use natural gas off the City’s existing meter for construction heat. The monthly usage would be compared to historical data, and Rice Lake would be responsible for the difference. Now that construction is nearing completion, the gas usage for the winters of 2023-2024 and 2024-2025 were compared to historical data and the difference was found to be $15,927.00. Therefore, a credit of $15,927.00 is being issued to the City of Otsego. Please let me know if you have any questions. Sincerely, Rice Lake Construction Group Matt Perpich Project Manager Outlook Otsego West - natural gas From Scott Schaefer <Scott.Schaefer@AE2S.com> Date Wed 7/9/2025 4:07 PM To Matt Perpich <matt_perpich@ricelake.org> Cc Sam Boelter <sam_boelter@ricelake.org>; John Larkin <John.Larkin@AE2S.com> Caution: This email originated from outside the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe. Matt – Finance Director preferred to process this as a change order. Below are the month-by-month stats. Increased Usage Billing Month Adjusted Therms Difference Rate/ therm Cost 9/1/2023 0 -209 $- 10/1/2023 314 -400 0.71676 $- 11/1/2023 2897 1414 0.65989 $932.88 12/1/2023 3552 664 0.74132 $492.59 1/1/2024 4903 1088 0.75868 $853.65 2/1/2024 3818 214 0.7821 $172.64 3/1/2024 3357 1079 0.63464 $712.37 4/1/2024 2126 698 0.59736 $435.23 9/1/2024 0 -209 $- 10/1/2024 129 -585 $- 11/1/2024 1621 138 0.70714 $100.91 12/1/2024 6234 3346 0.91348 $3,143.24 1/1/2025 6547 2732 0.91502 $2,720.39 2/1/2025 5777 2173 0.91563 $2,164.63 3/1/2025 4604 2326 0.84443 $2,151.44 4/1/2025 3399 1971 0.84265 $1,820.25 5/1/2025 620 243 0.8527 $226.34 Total $15,926.56 7/16/25, 2:53 PM Mail - Matt Perpich - Outlook https://outlook.office365.com/mail/inbox/id/AAQkADJkZjEzMGYxLWEzYjMtNDhkZi1hZjM3LTcwNGExNzdmYjI0MwAQAJ3HP1mgPU0emh4AVzrR8lk%…1/2